   Weekly progress report as on 06.01.2012
    
  Pier cap (Total no of pier Cap- 21) Completed 21 NOS COMPLETED
  RE Wall panel casting ( total600 nos) Completed  
  Slab calicut side  (total 10 nos ) In progress 9nos done  (adjacent span pending )
  slab NH side ( 11 nos) In progress 10nos done  (adjacent span pending )
  Retaining wall NH side In progress Done LHS -95%, RHS- 100%
  Dirt wall AP2 concreting  In progress Done 100%
  Dirt wall AP1 concreting  In progress Done 90%
  Handrail casting In progress 1000 nos completed.
  Handrail fixing In progress NH side 10 slab completed.
  Handrail fixing In progress CALICUT side 7 span over.
  Boring at RP4 Completed RP-4 FOUR pile concreted.
  Boring at RP3 In progress 1-PILE CONCRETED
  Boring at RP1 Completed RP-1 FOUR pile concreted.
  NH side RE panel erection In progress 90% completed.
  RE wall WORK. In progress 30% completed.
  expansion joint completed In progress AP1 balance
 
Back
 
    
REINFORCEMENT LOWERING.RP3-1.

    
    
RE WALL WORK CALICUT SIDE.

    
    
PAINTING WORK IN PROGRESS.

    
    
LINER PIT EXCAVATION.RP2-1.

    
 
    
EARTH FILLING IN RP2.

    
    
BORING IN RP3-1.

      
 

 

 

 

 

 

 

 