   Weekly progress report as on 06.01.2012
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

1

PILE THRIKKARIPUR  SIDE

33

33

Completed

2

PILE EZHIMALA SIDE

27

27

Completed

3

PILE PAYYANNUR SIDE

27

27

Completed

4

PILE CAP THRIKKARIPUR  SIDE

11

11

Completed

5

PILE CAP EZHIMALA SIDE

9

9

Completed

6

PILE CAP PAYYANNUR SIDE

9

9

Completed

9

PIER THRIKKARIPUR  SIDE

11

11

Completed

8

PIER EZHIMALA SIDE

9

9

Completed

9

PIER PAYYANNUR SIDE

9

9

Completed

10

PIER CAP THRIKKARIPUR  SIDE

11

11

Completed

11

PIER CAP EZHIMALA SIDE

9

9

Completed

12

PIER CAP PAYYANNUR SIDE

9

9

Completed

16

RE/R WALL THRIKKARIPUR  SIDE

100%

100%

Completed

17

RE/R WALL EZHIMALA SIDE

100%

100%

Completed

18

RE/R WALL PAYYANNUR SIDE

100%

70%

30%

30

10.00%

10.00%

10.00%

20.00%

28

BEAM/SLAB THRIKKARIPUR  SIDE

10

10

Completed

29

BEAM/SLAB EZHIMALA SIDE

7

7

Completed

30

BEAM/SLAB PAYYANNUR SIDE

10

8

Completed

31

HR/FP/KERB THRIKKARIPUR  SIDE

100%

100%

0%

15%

0.00%

10.00%

0.00%

30.00%

32

HR/FP/KERB EZHIMALA SIDE

100%

80%

20%

30%

10.00%

10.00%

0.00%

0.00%

33

HR/FP/KERB PAYYANNUR SIDE

100%

100%

0%

0

0.00%

0.00%

0.00%

0.00%

34

BC/PAINTING

100%

10%

90%

0

2.40%

2.40%

0.00%

3.00% 

 

Availbility of Men               
Date 31-12-2011 01-01-2012 02-01-2012 03-01-2012 04-01-2012 05-01-2012 06-01-2012
Nof labours 55 55 60 65 60 65 65 

 

Material Stocking Status Required Available
Coarse Aggreagate (m3) available  
Fine Aggreagate(m3) available  
Cement(bag) 300 400
Steel(MT) 3 12 

 

Utility shifting  
Utilities to be shifted Status
BSNL completed
KSEB completed
KWA completed
Others completed 

 

 
Back
 
    
VIEW TOWARDS EZHIMALA FRM P6

    
    
PAYYANNUR RETAINING WALL WORKS

    
    
EZHIMALA SIDE WBM

    
    
EZHIMALA SIDE HANDRAIL WORKS IP

    
 
    
AREA UNDER AP1-P6

      
 

 

 

 

 

 

 

 

Untitled Document