Prevoius Weekly Reports

   Weekly progress report as on 06.01.2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE SHORNUR  SIDE 9 9       Completed      
2 PILE M.C SIDE 36 36       Completed        
3 PILE CAP SHORNUR SIDE 3 3       Completed        
4 PILE CAP  M.C SIDE 12 12       Completed        
5 PIER SHORNUR  SIDE 3 3       Completed        
6 PIER M.C SIDE 12 12       Completed        
7 PIER CAP SHORNUR  SIDE 3 3       Completed        
8 PIER CAP M.C SIDE 12 12       Completed        
9 RCC WALL SHORNUR SIDE 100% 55 45% 0 15.00% 5.00% 63.00% 15.00% 0 Concreting of RCC wall completed on both sides.Filling and rolling of soil completed.Miscellaeous works steelbending in progress.
10 RE/R WALL M.C SIDE 100% 55 45% 0 15.00% 12.00% 13.00% 15.00% 0 RE wall erection and rolling completed for all layers.Coping beam work  shuttering in progress.Earthwork excavation for raft foundation in RCC  wall 
11 BEAM/SLAB SHORNUR SIDE 3 2 1 0 0 0 0 0 0  
12 BEAM/SLAB M.C SIDE 12 11 1 0 1 1 0 0 0 .Therefore deshuttering work of all spans (beam and deck slab) completed..
13 HR/FP/KERB SHORNUR  SIDE 100% 62 38% 0 0.00% 0.00% 0.00% 0.00% 0 days concreting of inner kerb of all the spans completed.
14 HR/FP/KERB M.C SIDE 100% 57 43% 0 10.00% 5.00% 6.00% 10.00%   Handrail fixing completed for P7-P8.Footpath slab concreting completed in 11 spans.
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%     

 

Availbility of Men               
Date 31-12-2011 12-01-2012 01-02-2012 01-03-2012 01-04-2012 01-05-2012 01-06-2012
Nof labours 22 22 20 20 20 20 20 

 

Material Stocking Status          
  Required Available Remarks    
Fine aggregate {cft} 300 400      
Cement(bag) 300 20 stock wil be replendished today    
Steel inT 7 8      
Coarse Aggreagate (cft) 300 350      

 

Utility shifting  
Utilities to be shifted  
BSNL COMPLETED
KSEB COMPLETED
KWA COMPLETED
Others COMPLETED 

 

 