Si No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
Remarks |
|
1 |
PILE KAINATTY SIDE |
18 |
18 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
|
2 |
PILE NADAPURAM SIDE |
27 |
27 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
|
3 |
PILE CAP KAINATTY SIDE |
6 |
6 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
|
4 |
PILE CAP NADAPURAM SIDE |
9 |
9 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
|
|
PIER KAINATTY SIDE |
6 |
6 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
|
6 |
PIER NADAPURAM SIDE |
9 |
9 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
|
7 |
PIER CAP KAINATTY SIDE |
6 |
6 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
|
8 |
PIER CAP NADAPURAM SIDE |
9 |
9 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
|
11 |
RE/R WALL KAINATTY SIDE |
100% |
45% |
55% |
55% |
15.00% |
15.00% |
0.00% |
15.00% |
|
On availability of red earth. |
|
10 |
RE/R WALL NADAPURAM SIDE |
100% |
55% |
45% |
45% |
15.00% |
10.00% |
5.00% |
20.00% |
|
|
|
12 |
BEAM/SLAB Staging Kainatty side |
6 |
5 |
1 |
1 |
1 |
1 |
1 |
0 |
|
|
|
13 |
BEAM/SLAB Bar bending and Fixing Kainatty side |
6 |
5 |
1 |
1 |
1 |
1 |
1 |
0 |
|
|
|
14 |
BEAM/SLAB Shuttering and Concreting Kainatty side |
6 |
4 |
2 |
2 |
1 |
0 |
1 |
0 |
|
|
|
15 |
BEAM/SLAB Staging Nadapuram side |
9 |
8 |
1 |
1 |
0 |
0 |
1 |
0 |
|
|
|
16 |
BEAM/SLAB Bar bending and Fixing Nadapuram side |
9 |
8 |
1 |
1 |
1 |
1 |
1 |
1 |
|
P6-P7 girder completed. |
|
17 |
BEAM/SLAB Shuttering and Concreting Nadapuram side |
9 |
8 |
1 |
1 |
1 |
0* |
1 |
1 |
|
P6-P7 girder completed. |
|
18 |
BEAM/SLAB KAINATTY SIDE |
6 |
4 |
2 |
2 |
1 |
0 |
2 |
0 |
|
|
|
19 |
BEAM/SLAB NADAPURAM SIDE |
9 |
8 |
1 |
1 |
1 |
1 |
2 |
1 |
|
Steel work for P6-P7 slab in progress. |
|
20 |
HR/FP/KERB KAINATTY SIDE |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
|
21 |
HR/FP/KERB NADAPURAM SIDE |
100% |
80% |
20% |
20% |
10.00% |
5.00% |
5.00% |
10.00% |
|
|
|
22 |
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
|
|
Note: Progress review done based on the revised Program (rev-01) |
|
|
|
|
|
|
|
|
Availbility of Men |
|
|
|
|
|
|
|
|
|
|
|
|
Date |
|
31-12-11 |
########## |
01-02-2012 |
01-03-2012 |
01-04-2012 |
01-05-2012 |
01-06-2012 |
|
|
|
|
Nof labours |
|
55 |
55 |
55 |
50 |
50 |
50 |
50 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Material Stocking Status |
Required |
Available |
Remarks |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fine Aggreagate(m3) |
45 |
30 |
|
|
|
|
|
|
|
|
|
|
Cement(bag) |
850 |
1300 |
|
|
|
|
|
|
|
|
|
|
Steel(MT) |
16 |
25 |
|
|
|
|
|
|
|
|
|
|
Coarse Aggreagate (m3) |
95 |
60 |
|
|
|
|
|
|
|
|
|
|
Utility shifting |
|
|
|
|
|
|
|
|
|
|
|
|
Utilities to be shifted |
Status |
Remarks |
|
|
|
|
|
|
|
|
|
|
BSNL |
in progress |
|
|
|
|
|
|
|
|
|
|
|
KSEB |
shifted |
|
|
|
|
|
|
|
|
|
|
|
KWA |
shifted |
|
|
|
|
|
|
|
|
|
|
|
Others |
shifted |
|
|
|
|
|
|
|
|
|
|