Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8051498
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly Progress Report as on 06.01.2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks   
1 PILE KAINATTY  SIDE 18 18 0 0 0 0 0 0      
2 PILE NADAPURAM SIDE 27 27 0 0 0 0 0 0      
3 PILE CAP KAINATTY SIDE 6 6 0 0 0 0 0 0      
4 PILE CAP  NADAPURAM SIDE 9 9 0 0 0 0 0 0      
  PIER KAINATTY  SIDE 6 6 0 0 0 0 0 0      
6 PIER NADAPURAM SIDE 9 9 0 0 0 0 0 0      
7 PIER CAP KAINATTY  SIDE 6 6 0 0 0 0 0 0      
8 PIER CAP NADAPURAM SIDE 9 9 0 0 0 0 0 0      
11 RE/R WALL KAINATTY  SIDE 100% 45% 55% 55% 15.00% 15.00% 0.00% 15.00%   On availability of red earth.  
10 RE/R WALL NADAPURAM SIDE 100% 55% 45% 45% 15.00% 10.00% 5.00% 20.00%      
12 BEAM/SLAB  Staging Kainatty side 6 5 1 1 1 1 1 0      
13 BEAM/SLAB  Bar bending and Fixing Kainatty side 6 5 1 1 1 1 1 0      
14 BEAM/SLAB  Shuttering  and Concreting  Kainatty side 6 4 2 2 1 0 1 0      
15 BEAM/SLAB  Staging Nadapuram side 9 8 1 1 0 0 1 0      
16 BEAM/SLAB  Bar bending and Fixing Nadapuram side 9 8 1 1 1 1 1 1   P6-P7 girder completed.  
17 BEAM/SLAB  Shuttering  and Concreting  Nadapuram side 9 8 1 1 1 0* 1 1   P6-P7 girder completed.  
18 BEAM/SLAB KAINATTY  SIDE 6 4 2 2 1 0 2 0      
19 BEAM/SLAB NADAPURAM SIDE 9 8 1 1 1 1 2 1   Steel work for P6-P7 slab in progress.  
20 HR/FP/KERB KAINATTY  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%      
21 HR/FP/KERB NADAPURAM SIDE 100% 80% 20% 20% 10.00% 5.00% 5.00% 10.00%      
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%      
  Note: Progress review done based on the revised Program (rev-01)              
  Availbility of Men                       
  Date   31-12-11 ########## 01-02-2012 01-03-2012 01-04-2012 01-05-2012 01-06-2012      
  Nof labours   55 55 55 50 50 50 50      
                         
  Material Stocking Status Required Available Remarks                
                         
  Fine Aggreagate(m3) 45 30                  
  Cement(bag) 850 1300                  
  Steel(MT) 16 25                  
  Coarse Aggreagate (m3) 95 60                  
  Utility shifting                      
  Utilities to be shifted Status Remarks                  
  BSNL in progress                    
  KSEB shifted                    
  KWA shifted                    
  Others shifted                    
                     
 
Back
 
    
RE WALL AT KAINATTY SIDE

    
    
REWALL AT NADAPURAM SIDE

    
    
RE WALL EXCAVATION AT NADAPURAM SIDE

    
    
STEEL WORK FOR GRIDER P4-P5

    
 
    
DIRTWALL STEEL WORK-KAINATTY SIDE

      
 

 

 

 

 

 

 

 

Untitled Document