   weekly progress 6.1.2012
    

 

Progress Report For ROB Puliyanam for the week ending on 06/01/2012
Sl No   Activity Description   Total Quantity  Cumulative progress upto last week   Balance  work up to last week  Cumulative delay in Qty up to last week  Work  planned  during the week   Actual work done during the week   Cumulative delay in Qty up to this week  Work  Planned for next week   Remarks 
1 Pile towards NH side 26 26 0 0 0 0 0 0 TARGET ACHIEVED
2 Pile towards Puliyanam side 18 18 0 0 0 0 0 0 TARGET ACHIEVED
3 Pile cap at NH  Side 6 6 0 0 0 0 0 0 TARGET ACHIEVED
4 Pile Cap at Puliyanamside 4 4 0 0 0 0 0 0 TARGET ACHIEVED
5 RC wall at Puliyanam side 100% 80% 20% 0 5% 5% 0% 5%  
6 RC wall at NH side 100% 70% 30% 0 10% 5% 0% 5%  
7 Pier at NH Side 6 6 0 0 0 0 0 0 TARGET ACHIEVED
8 Pier at Puliyanam Side 4 4 0 0 0 0 0 0 TARGET ACHIEVED
9 Piercap at NH Side 6 6 0 0 0 1 0 0 TARGET ACHIEVED
10 Piercap at Puliyanam 4 4 0 0 0 0 0 0 TARGET ACHIEVED
11 PEDESTAL 54 45 9 9 0 0 9 9  
12 Beam and cross beam at NH side 6 1 5 0 0 0 0 1  
13 Beam and cross beam at Puliyanam side  4 0 4 0 0 0 0 0  
14 Deck slab  at NH side  6 1 5 0 0 1 0 0  
15 Deck slab  at Puliyanam side  4 0 4 0 0 0 0 0   

 

Date 31.12.11 02.01.12 03.01.12 04.01.12 05.01.12 06.01.12
Climate pleasant pleasant pleasant pleasant pleasant pleasant
No.of labours 73 67 67 69 68 69
             
availability of material          
materials Required Available        
Fine aggregate(M3) 30 50        
Coarse aggregate(M3) 50 60        
Cement(BAG) 500 700        
Steel(TONN) 16 55        
             
 
Back
 
    
NH SIDE RC WALL STEM CONCRETE ,05.01.2012

    
    
READY MIX FOR SAB P8-P9 CONCRETE.31.12.2011

    
    
REINFORCEMENT WORK FOR BEAM P9-P10,02.01.2012

    
    
REINFORCEMENT WORK FOR NH SIDE RC WALL ,06.01.2012

    
 
    
SLAB P8-P9 CONCRETE ,31.12.2011

    
    
STAGING FOR SPAN A1-P1,04.01.2012.

      
 

 

 

 

 

 

 

 