   Weekly progress report as on 30.12.2011
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PILE SHORNUR  SIDE

9

9

 

 

 

Completed

 

 

 

2

PILE M.C SIDE

36

36

 

 

 

Completed

 

 

 

 

3

PILE CAP SHORNUR SIDE

3

3

 

 

 

Completed

 

 

 

 

4

PILE CAP  M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

5

PIER SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

 

6

PIER M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

7

PIER CAP SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

 

8

PIER CAP M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

9

RCC WALL SHORNUR SIDE

100%

55

45%

0

15.00%

8.00%

63.00%

15.00%

0

Concreting of RCC wall completed on both sides.Filling and rolling of soil as the balance work.Clearing of RCC wall portion in portion

10

RE/R WALL M.C SIDE

100%

10

90%

0

25.00%

20.00%

13.00%

25.00%

0

Erection and aligning of six layers out of the seven layers of the RE Panels completed. Rolling and filling of five layers completed.Road deviation work for RCC wall commencement completed.

11

BEAM/SLAB SHORNUR  SIDE

3

2

1

0

0

0

0

0

0

 

12

BEAM/SLAB M.C SIDE

12

11

1

0

1

1

0

0

0

.Therefore deshuttering work of all spans (beam and deck slab) completed..

13

HR/FP/KERB SHORNUR  SIDE

100%

62

38%

0

0.00%

0.00%

0.00%

0.00%

0 days

concreting of inner kerb of all the spans completed.

14

HR/FP/KERB M.C SIDE

100%

57

43%

0

10.00%

5.00%

6.00%

10.00%

 

Handrail fixing completed for P7-P8.Footpath slab concreting completed in P5-P4,P3-P4.

15

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

  

 

Availbility of Men                 
Date 24-12-2011 25-12-2011 26-12-2011 27-12-2011 28-12-2011 29-12-2011 30-12-2011  
Nof labours 22 22 20 20 20 20 20  
                 
Material Stocking Status                
  Required Available Remarks          
Fine aggregate {cft} 300 400            
Cement(bag) 300 80 stock wil be replendished today          
Steel inT 7 9            
Coarse Aggreagate (cft) 300 350 stock wil be replendished today          

 

Utility shifting  
Utilities to be shifted  
BSNL COMPLETED
KSEB COMPLETED
KWA COMPLETED
Others COMPLETED 

 

 