   Weekly progress report as on 30.12.2011
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

Remarks

1

PILE CHERUVATHOOR  SIDE

27

21

6

1

1

0

2

2

 

2

PILE PADANNA SIDE

24

20

4

2

1

1

3

0

 

3

PILE CAP CHERUVATHOOR SIDE

9

7

2

1

0

0

0

0

 

4

PILE CAP  PADANNA SIDE

8

5

3

0

1

0

1

1

 

5

PIER CHERUVATHOOR SIDE

9

6

3

0

0

0

0

0

Pier P11 3rd lift complete

6

PIER PADANNA SIDE

8

0

8

2

3

2.5

1

2

P5 Pier fist lift complete

7

PIER CAP CHERUVATHOOR SIDE

9

5

4

0

1

0

1

0

P12 pier cap complete

8

PIER CAP PADANNA SIDE

8

0

8

0

0

0

0

2

 

9

RE/R WALL CHERUVATHOOR  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

10

RE/R WALL PADANNA SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

11

BEAM/SLAB CHERUVATHOOR  SIDE

9

1

8

0

0.5

0

0.5

1

P15-P14 girder shuttering work IP

12

BEAM/SLAB PADANNA SIDE

8

0

8

0

0

0

0

0

 

13

HR/FP/KERB CHERUVATHOOR  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

14

HR/FP/KERB PADANNA SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

15

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

  

 

Availbility of Men             
Date 24-12-2011 25-12-2011 26-12-2011 27-12-2011 28-12-2011 29-12-2011 30-12-2011
No of labours 45 20 45 18 45 51 51 

 

Material Stocking Status Required Available
Coarse Aggreagate (m3) available  
Fine Aggreagate(m3) available  
Cement(bag) 700 1144
Steel(MT) 15 30 

 

Utility shifting    
Utilities to be shifted Status Remarks
BSNL AP1,P10 to be shifted.P10 shifting in progress
KSEB in progress estimation yet to be received,P1 and P10 location cleared.
KWA currently can be managed at site    

 

  AREAS OF  CONCERN AND CORRECTIVE ACTION:        
             
1 P9 building demolition complete.
             
2 Land acquisition at AP1(BSNL) not yet done.At Padanna side, no workfront after PI location .
             
3 BSNL cables to be shifted at P10 location.It can be shifted only after diverting the road from P11.  
  Earth filling for road diversion in progress.        

 

 
Back
 
    
SHUTTERING WORK OF P15-P14 GIRDER

    
    
P9 LOCATION

    
    
P5 PIER FIRST LIFT CONCRETE COMPLETE

    
    
P3&P2 PIERS COMPLETE

    
 
    
P1B PILE CONCRETE COMPLETE

      
 

 

 

 

 

 

 

 