Service road on kanjippuram side |
Completed |
for piling. |
Piling |
In progress |
Completed 30 nos (P11-3, P12-3,P17-3,P19-3,P13-3, P18-3,AP2-3, P14-3, P15-3 P16-3) |
Pile cap |
In progress |
Completed 6 nos(P11,P12,P13,P14,P15,P16) |
Reinforcement for Pile cap P14 |
In progress |
|
Load testing for P19 a |
completed |
|
|
|