Sl No |
Activity Description |
Total Quantity |
Cumulative progress upto 29.12.11 |
Balance work up to 29.12.11 |
Cumulative delay in Qty up to 29.12.11 |
Work planned during the week |
Actual work done during the week |
Delay in Qty up to this week |
Work Planned for next week |
1 |
PILE Pettah side(Approach portion) |
12 |
12 |
0 |
0 |
1 |
1 |
0 |
0 |
2 |
PILE Anayara side(Approach portion) |
12 |
3 |
9 |
2 |
3 |
1 |
2 |
4 |
3 |
PILE CAP Pettah side(Approach portion) |
4 |
1 |
3 |
1 |
2 |
1 |
1 |
1 |
4 |
PILE CAP Anayara side(Approach portion) |
4 |
|
4 |
|
|
|
|
|
5 |
PIER Pettah side(Approach portion) |
4 |
|
4 |
|
|
|
|
|
6 |
PIER Anayara side(Approach portion) |
4 |
|
4 |
|
|
|
|
|
7 |
PIER CAP Pettah side(Approach portion) |
4 |
|
4 |
|
|
|
|
|
8 |
GIRDER Pettah side(Approach portion) |
4 |
|
4 |
|
|
|
|
|
9 |
GIRDER Anayara side(Approach portion) |
4 |
|
4 |
|
|
|
|
|
10 |
Service Road Pettah side(Approach portion) |
1400 |
350 |
1050 |
|
|
|
|
|
11 |
Service Road Anayara side(Approach portion) |
1400 |
350 |
1050 |
|
|
|
|
|