   Weekly progress report as on 30.12.2011
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  Remarks 
1 PILE  CALICUT  SIDE 48 48 0 0 0 0 1 0  
2 PILE THIRUR SIDE 24 19 5 0 2 1 7 3  
3 PILE CAP CALICUT  SIDE 12 12 0 0 0 0 1 0  
4 PILE CAP  THIRURSIDE 6 0 6 0 0 0 0 2  
5 PIER CALICUT SIDE 12 12 0 0 1 0 1 0  
6 PIER THIRUR SIDE 6 0 6 0 0 0 0 0  
7 PIER CAPCALICUT   SIDE 12 8 4 0 2 0 2 2 staging @ p5,p6 completed
8 PIER CAP THIRUR SIDE 6 0 6 0 0 0 0 0  
9 RE/R WALL CALICUT   SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
10 RE/R WALLTHIRUR SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
11 BEAM/SLAB CALICUT   SIDE 12 0 12 0 0 0 0 0  
12 BEAM/SLAB THIRUR SIDE 6 0 6 0 0 0 0 0  
13 HR/FP/KERB CALICUT   SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
14 HR/FP/KERBTHIRUR SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%  
16 Deck Slab                  
17 Utility shifting                  
                     
                     
                     
  Availbility of Men                 
  Date 23-12-2011 24-12-2011 25-12-2011 26-12-2011 27-12-2011 28-12-2011 29-12-2011    
  Nof labours 30 0 0 29 32 32 32    
                     
  Material Stocking Status Required Available Remarks            
  Coarse Aggreagate (m3) 28 21              
  Fine Aggreagate(m3) 18 10              
  Cement(bag) 450 190              
  Steel(MT)   16              
                     
                     
  Utility shifting                  
  Utilities to be shifted Status Remarks              
  BSNL shifting completed                
  KSEB shifting in progress                
  KWA shifting completed                
  Others                  
 
Back
 
    
STAGING FOR GIRDER @ P6 P7

    
    
REINFORCEMENT LOWERING @ A2

    
    
RAILWAY PILE REINFORCEMENT @ TIRUR SIDE

    
    
PEDESTAL WALL @ A1

    
 
    
PEDESTAL REINFORCEMENT @ P5

    
    
ARRANGEMENTS FOR STAGING BTWN P6 & P7

      
 

 

 

 

 

 

 

 