Si No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
Remarks |
1 |
PCC for RAFT MOYAN SIDE |
3 |
3 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
2 |
PCC for RAFT PALAKKAD SCHOOL SIDE |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
3 |
RAFT PALAKKAD SIDE |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
4 |
RAFT MOYAN SCHOOL SIDE |
3 |
3 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
5 |
PIER PALAKKAD SIDE |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
6 |
PIER MOYAN SCHOOL SIDE |
3 |
3 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
7 |
PIER CAP PALAKKAD SIDE |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
8 |
PIER CAP MOYAN SCHOOL SIDE |
3 |
3 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
9 |
RE/R WALL PALAKKAD SIDE |
100% |
95% |
5% |
0 |
0.00% |
0.00% |
5.00% |
5.00% |
|
|
10 |
RE/R WALL MOYAN SCHOOL SIDE |
100% |
100% |
0% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
11 |
BEAM/SLAB Staging Palakad SIDE |
2 |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
12 |
BEAM/SLAB Bar bending and Fixing Palakad SIDE |
2 |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
13 |
BEAM/SLAB Shuttering and Concreting Palakad SIDE |
2 |
2 |
0 |
0 |
0 |
0 |
0 |
o |
|
|
14 |
BEAM/SLAB Staging Moyan schoolSIDE |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
15 |
BEAM/SLAB Bar bending and Fixing Moyan school SIDE |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
16 |
BEAM/SLAB Shuttering and Concreting Moyan school SIDE |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
17 |
BEAM/SLAB PALAKKAD SIDE |
2 |
2 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
18 |
BEAM/SLAB MOYAN SCHOOL SIDE |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
19 |
BEAM/SLAB RAILWAY SPAN |
7 |
3 |
4 |
0 |
0 |
0 |
0 |
0 |
|
|
20 |
HR/FP/KERB Pkd SIDE |
100% |
90% |
10% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
21 |
HR/FP/KERB Moyen's SIDE |
100% |
95% |
5% |
0 |
0.00% |
30.00% |
0.00% |
5.00% |
|
|
22 |
HR/FP/KERB RAILWAY SPAN |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
5.00% |
5.00% |
|
|
23 |
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Note: Progress review done based on the revised Program (rev-01) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
ROB Sulthanpet, Palakkad |
|
|
|
|
|
|
|
|
|
|
|
Date |
Barbenders |
Mechanics/Electricains |
Helpers |
Ret. Wall work |
|
|
|
|
|
|
|
24/12/2011 |
24 |
5 |
10 |
8 |
|
|
|
|
|
|
|
25/12/2011 |
- |
- |
- |
- |
|
|
|
|
|
|
|
26/12/2011 |
24 |
5 |
10 |
7 |
|
|
|
|
|
|
|
27/12/2011 |
25 |
5 |
10 |
8 |
|
|
|
|
|
|
|
28/12/2011 |
35 |
9 |
21 |
8 |
|
|
|
|
|
|
|
29/12/2011 |
25 |
9 |
21 |
7 |
|
|
|
|
|
|
|
30/12/2011 |
9 |
4 |
7 |
8 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Material Stocking Status |
|
|
|
|
|
|
|
|
|
|
Required |
Available |
|
|
|
|
|
|
|
|
|
Fine agg. {m³} |
4 |
16 |
|
|
|
|
|
|
|
|
|
Cement(bag) |
75 |
450 |
|
|
|
|
|
|
|
|
|
Steel in T |
2 |
45 |
|
|
|
|
|
|
|
|
|
Coarse agg. (m3) |
7 |
21 |
|
|
|
|
|
|
|
|