Prevoius Weekly Reports

   Weekly progress report as on 30.12.2011
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

1

PILE THRIKKARIPUR  SIDE

33

33

Completed

2

PILE EZHIMALA SIDE

27

27

Completed

3

PILE PAYYANNUR SIDE

27

27

Completed

4

PILE CAP THRIKKARIPUR  SIDE

11

11

Completed

5

PILE CAP EZHIMALA SIDE

9

9

Completed

6

PILE CAP PAYYANNUR SIDE

9

9

Completed

9

PIER THRIKKARIPUR  SIDE

11

11

Completed

8

PIER EZHIMALA SIDE

9

9

Completed

9

PIER PAYYANNUR SIDE

9

9

Completed

10

PIER CAP THRIKKARIPUR  SIDE

11

11

Completed

11

PIER CAP EZHIMALA SIDE

9

9

Completed

12

PIER CAP PAYYANNUR SIDE

9

9

Completed

16

RE/R WALL THRIKKARIPUR  SIDE

100%

100%

Completed

17

RE/R WALL EZHIMALA SIDE

100%

100%

Completed

18

RE/R WALL PAYYANNUR SIDE

100%

60%

40%

30

10.00%

10.00%

10.00%

20.00%

28

BEAM/SLAB THRIKKARIPUR  SIDE

10

10

Completed

29

BEAM/SLAB EZHIMALA SIDE

7

7

Completed

30

BEAM/SLAB PAYYANNUR SIDE

10

8

Completed

31

HR/FP/KERB THRIKKARIPUR  SIDE

100%

100%

0%

15%

0.00%

10.00%

0.00%

30.00%

32

HR/FP/KERB EZHIMALA SIDE

100%

70%

30%

30%

10.00%

10.00%

0.00%

0.00%

33

HR/FP/KERB PAYYANNUR SIDE

100%

100%

0%

0

0.00%

0.00%

0.00%

0.00%

34

BC/PAINTING

100%

10%

90%

0

2.40%

2.40%

0.00%

3.00% 

 

Availbility of Men               
Date 24-12-2011 25-12-2011 26-12-2011 27-12-2011 28-12-2011 29-12-2011 30-12-2011
Nof labours 70 70 70 70 55 55 55 

 

Material Stocking Status Required Available
Coarse Aggreagate (m3) available  
Fine Aggreagate(m3) available  
Cement(bag) 200 350
Steel(MT) 3 12 

 

Utility shifting  
Utilities to be shifted Status
BSNL completed
KSEB completed
KWA completed
Others completed 

 

Description Progress  Remarks 
Pier cap concreting (Total no of pier cap- 29) completed  
Slab  Thrikkaripur side (  10 nos) completed 10 nos done
Slab Ezhimala side ( 7 nos) completed 7nos done
Slab Payyanur side ( 10 nos) Remaining two can be done
only after railway portion is done
8 nos done
Retaining wall/RE wall panel casting- Ezhimala side completed  
Retaining wall Thrikkaripur side  completed  
Retaining wall Payyannur side  In progress Dne 60%
Handrail & Kerb payyannur side completed  
Handrail & Kerb Thrikaripur side completed  
Handrail & Kerb Ezhimala side In progress all except approach
Expansion joint: Payyannur side In progress 1 LEFT
Expansion joint: Ezhimala side completed  
Expansion joint: Thrikkarippur side completed  
Kerb completed (total 25 spans complete)
Painting  In progress Total 18 spans completed 

 

 