   weekly progress 30.12.2011
    

 

Sl No   Activity Description   Total Quantity  Cumulative progress upto last week   Balance  work up to last week  Cumulative delay in Qty up to last week  Work  planned  during the week   Actual work done during the week   Cumulative delay in Qty up to this week  Work  Planned for next week   Remarks 
1 Pile towards NH side 26 26 0 0 0 0 0 0 TARGET ACHIEVED
2 Pile towards Puliyanam side 18 18 0 0 0 0 0 0 TARGET ACHIEVED
3 Pile cap at NH  Side 6 6 0 0 0 0 0 0 TARGET ACHIEVED
4 Pile Cap at Puliyanamside 4 4 0 0 0 0 0 0 TARGET ACHIEVED
5 RC wall at Puliyanam side 100% 75% 25% 0 0% 5% 0% 5%  
6 RC wall at NH side 100% 65% 35% 0 0% 10% 0% 10%  
7 Pier at NH Side 6 6 0 0 0 0 0 0 TARGET ACHIEVED
8 Pier at Puliyanam Side 4 4 0 0 0 0 0 0 TARGET ACHIEVED
9 Piercap at NH Side 6 6 0 0 0 1 0 0 TARGET ACHIEVED
10 Piercap at Puliyanam 4 4 0 0 0 0 0 0 TARGET ACHIEVED
11 PEDESTAL 54 45 9 0 0 6 0 9  
12 Beam and cross beam at NH side 6 1 5 0 0 0 0 0  
13 Beam and cross beam at Puliyanam side  4 0 0 0 0 0 0 0  
                     
Date 24.12.11 26.12.11 27.12.11 28.12.11 29.12.11 30.12.11        
Climate pleasant pleasant pleasant pleasant pleasant pleasant        
No.of labours 68 67 67 82 68 69        
                     
availability of material                  
materials Required Available                
Fine aggregate(M3) 16 18                
Coarse aggregate(M3) 17 22                
Cement(BAG) 500 700                
Steel(TONN) 9 55                
 
Back
 
    
SHUTTERING FOR SLAB P8-P9, 27.12.2011.

    
    
STEEL WORK FOR BEAM P9-P10, 30.12.2011

    
    
SHUTTERING FOR SLAB P8-P9, 27.12.2011.

    
    
STEEL WORK FOR SLAB P8-P9, 29.12.2011

    
 
    
PIER CAP P6, CONCRETED 28.12.2011

      
 

 

 

 

 

 

 

 