   Weekly progress report as on 23.12.2011
    
 

Progress Report For Koilandy ROB for the week ending on 23-12-2011

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

1

PILE Muthambi side

27

18

9

0

0

0

0

2

2

PILE Thamarassery side

33

28

5

0

6

4

0

2

3

PILE NH SIDE

30

21

9

0

1

1

0

2

4

PILE CAP Muthambi SIDE

9

5

4

0

i

0

0

1

4

PILE CAP Thamarassery SIDE

11

0

11

0

2

0

0

1

5

PILE CAP NH SIDE

10

2

8

0

2

2

0

2

6

PIER Muthambi  SIDE

9

5

4

0

1

2

0

1

7

PIER Thamarassery SIDE

11

0

11

0

0

0

0

0

8

PIER NH SIDE

10

1

9

0

1

1

0

2

9

PIER CAP Muthambi  SIDE

9

3

6

0

2

2

0

2

10

PIER CAP Thamarassery SIDE

11

0

11

0

0

0

0

1

11

PIER CAP NH SIDE

10

0

10

0

0

0

0

0

12

RE/R WALL Muthambi side

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

13

RE/R WALL Thamarassery side SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

14

RE/R WALL NH SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

15

BEAM/SLAB Muthambi SIDE

8

0

8

0

0

0

0

0

16

BEAM/SLAB Thamarassery SIDE

10

0

10

0

0

0

0

0

17

BEAM/SLABNH SIDE

10

0

10

0

0

0

0

0

18

HR/FP/KERB Muthambi SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

19

HR/FP/KERB thamarassery SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

20

HR/FP/KERB NH SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

21

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00% 

 

Availbility of Men               
Date 17/12/2011 18/12/2011 19/12/2011 20/12/2011 21/12/2011 22/12/2011 23/12/2011
Nof labours 55 55 55 55 55 55 55 

 

Material Stocking Status Required Available
Coarse Aggreagate (m3) 110 100
Fine Aggreagate(m3) 110 100
Cement(bag) 1200 2000
Steel(MT) 18 30 

 

 
Back
 
    
STAGING IN PROGRESS BWTWEEN P14 &P15

    
    
STAGING FOR P14-P15 GIRDER CONCRETEING

    
    
P15 PIERCAP CONCRETING DONE

    
    
P14 PIERCAP REINFORCEMENT WORK IN PROGRESS

    
 
    
P1 PILECAP READY FOR CONCRETE

    
    
AP1A - PILECAP CONCRETING

      
 

 

 

 

 

 

 

 