   Weekly progress report as on 23.12.2011
    
 

Progress Report For Cheruvathoor  ROB for the week ending on 23-12-2011

 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PILE CHERUVATHOOR  SIDE

27

21

6

2

0

0

0

1

 

 

2

PILE PADANNA SIDE

24

18

6

2

2

2

3

1

 

 

3

PILE CAP CHERUVATHOOR SIDE

9

7

2

1

0

0

0

0

 

 

4

PILE CAP  PADANNA SIDE

8

5

3

0

0

0

0

1

 

 

5

PIER CHERUVATHOOR SIDE

9

5

4

0

1

1

0

0

 

Pier P11 2nd lift complete

6

PIER PADANNA SIDE

8

0

8

0

3

0

3

3

 

 

7

PIER CAP CHERUVATHOOR SIDE

9

4

5

0

2

1

1

1

 

P12 pier cap complete

8

PIER CAP PADANNA SIDE

8

0

8

0

0

0

0

0

 

 

9

RE/R WALL CHERUVATHOOR  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

10

RE/R WALL PADANNA SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

11

BEAM/SLAB CHERUVATHOOR  SIDE

9

0

9

0

1

1

0

0.5

 

 AP2-P15 slab complete,staging for P15-P14 girder in progress

12

BEAM/SLAB PADANNA SIDE

8

0

8

0

0

0

0

0

 

 

13

HR/FP/KERB CHERUVATHOOR  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

14

HR/FP/KERB PADANNA SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

15

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

  

 

Availbility of Men               
Date 17-12-2011 18-12-2011 19-12-2011 20-12-2011 21-12-2011 22-12-2011 23-12-2011
No of labours 50 15 52 52 45 56 52 

 

Material Stocking Status Required Available
Coarse Aggreagate (m3) available  
Fine Aggreagate(m3) available  
Cement(bag) 800 1500

 

  AREAS OF  CONCERN AND CORRECTIVE ACTION:      
             
1 P9 building demolition in progress.
             
2 Land acquisition at AP1(BSNL) not yet done.At Padanna side, no workfront after PI location .
             
3 BSNL cables to be shifted at P10 location.It can be shifted only after diverting the road from P11.  
  Earth filling for road diversion in progress.        

 

 

 
Back
 
    
PILE CAP EXCAVATION AT P4 LOCATION

    
    
P15-P14 GIRDER STAGING IP

    
    
P12 PIER CAP

    
    
P11 PIER 2ND LIFT COMPLETE

    
 
    
BORING IP AT P1B LOCATION

    
    
BORING IP AT P1B LOCATION

    
    
AP2-P15 DECK SLAB CONCRETING

    
 
 
 

 

 

 

 

 

 

 