   Weekly progress report as on 23.12.2011
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

1

PILE THRIKKARIPUR  SIDE

33

33

Completed

2

PILE EZHIMALA SIDE

27

27

Completed

3

PILE PAYYANNUR SIDE

27

27

Completed

4

PILE CAP THRIKKARIPUR  SIDE

11

11

Completed

5

PILE CAP EZHIMALA SIDE

9

9

Completed

6

PILE CAP PAYYANNUR SIDE

9

9

Completed

9

PIER THRIKKARIPUR  SIDE

11

11

Completed

8

PIER EZHIMALA SIDE

9

9

Completed

9

PIER PAYYANNUR SIDE

9

9

Completed

10

PIER CAP THRIKKARIPUR  SIDE

11

11

Completed

11

PIER CAP EZHIMALA SIDE

9

9

Completed

12

PIER CAP PAYYANNUR SIDE

9

9

Completed

16

RE/R WALL THRIKKARIPUR  SIDE

100%

100%

Completed

17

RE/R WALL EZHIMALA SIDE

100%

55%

45%

0

5.00%

5.00%

0.00%

5.00%

18

RE/R WALL PAYYANNUR SIDE

100%

10

90%

0

0.00%

0.00%

0.00%

0.00%

28

BEAM/SLAB THRIKKARIPUR  SIDE

10

10

Completed

29

BEAM/SLAB EZHIMALA SIDE

7

7

Completed

30

BEAM/SLAB PAYYANNUR SIDE

10

8

Completed

31

HR/FP/KERB THRIKKARIPUR  SIDE

100%

85%

15%

15%

0.00%

10.00%

0.00%

30.00%

32

HR/FP/KERB EZHIMALA SIDE

100%

70%

30%

30%

10.00%

10.00%

0.00%

0.00%

33

HR/FP/KERB PAYYANNUR SIDE

100%

100%

0%

0

0.00%

0.00%

0.00%

0.00%

34

BC/PAINTING

100%

10%

90%

0

2.40%

2.40%

0.00%

3.00% 

 

Availbility of Men               
Date 17-12-2011 18-12-2011 19-12-2011 20-12-2011 21-12-2011 22-12-2011 23-12-2011
Nof labours 56 70 70 70 70 70 70 

 

Material Stocking Status Required Available
Coarse Aggreagate (m3) available  
Fine Aggreagate(m3) available  
Cement(bag) 300 500
Steel(MT) 5 12 

 

Utility shifting  
Utilities to be shifted Status
BSNL completed
KSEB completed
KWA completed
Others completed 

 

Description Progress/Completed Remarks

Pier cap concreting (Total no of pier cap- 29)

completed

 

Slab  Thrikkaripur side (  10 nos)

completed

10 nos done

Slab Ezhimala side ( 7 nos)

completed

7nos done

Slab Payyanur side ( 10 nos)

Remaining two can be done
only after railway portion is done

8 nos done

Retaining wall/RE wall panel casting- Ezhimala side

In progress

done 75%

Retaining wall Thrikkaripur side

In progress

Done 95%

Retaining wall Payyannur side

In progress

Dne 40%

Handrail & Kerb payyannur side

completed

 

Handrail & Kerb Thrikaripur side

In progress

AP1-1-2-3-4-5-6-7-8 completed

Handrail & Kerb Ezhimala side

In progress

P9-10-11,11-12,12-13,13-14-15-16-AP2

Expansion joint: Payyannur side

In progress

1 LEFT

Expansion joint: Ezhimala side

completed

All Including approach

Expansion joint: Thrikkarippur side

completed

All Including approach

Kerb

completed

(total 25 spans complete)

Painting

In progress

Total 15 spans completed 

 

 
Back
 
    
RAILWAY PIER CAP PEDESTAL WORKS

    
    
MASTIC WORK IP

    
    
EZHIMALA SIDE KERB WORKS IP

    
    
EZHIMALA SIDE CLEANING IP

    
 
    
BM PLANT FINAL WORKS IP

      
 

 

 

 

 

 

 

 