Prevoius Weekly Reports

   Weekly Progress Report as on23.12.11
    

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PILE SHORNUR  SIDE

9

9

 

 

 

Completed

 

 

 

2

PILE M.C SIDE

36

36

 

 

 

Completed

 

 

 

 

3

PILE CAP SHORNUR SIDE

3

3

 

 

 

Completed

 

 

 

 

4

PILE CAP  M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

5

PIER SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

 

6

PIER M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

7

PIER CAP SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

 

8

PIER CAP M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

9

RCC WALL SHORNUR SIDE

100%

55

45%

0

20.00%

8.00%

63.00%

15.00%

0

Concreting of RCC retaining wall (complete 1 side).Raft concreting completed for 22 metres on one side.Concreting of the first lift of the RCC wall completed this week.Concreting of the balance (complete) will be completed this week.

10

RE/R WALL M.C SIDE

100%

10

90%

0

25.00%

25.00%

13.00%

25.00%

0

Erection of the three layers out of the total  seven layers completed.Levelling and rolling (compaction) of two layers completed .The third layer will be completed today

11

BEAM/SLAB SHORNUR  SIDE

3

2

1

0

0

0

0

0

0

 

12

BEAM/SLAB M.C SIDE

12

11

1

0

1

1

0

0

0

.Therefore deshuttering work of all spans (beam and deck slab) completed..

13

HR/FP/KERB SHORNUR  SIDE

100%

62

38%

0

0.00%

0.00%

0.00%

0.00%

0 days

concreting of inner kerb of all the spans completed.

14

HR/FP/KERB M.C SIDE

100%

57

43%

0

10.00%

5.00%

6.00%

10.00%

 

Precast footpath slab casting started and completed for two spans.(AP2-P13,P13-P12).Footpath slab(cast in situ)  completed for P6-P5 ,P6-P7.

15

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

16

Deck Slab

 

 

 

 

 

 

 

 

 

 

17

Utility shifting

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Availbility of Men

 

 

 

 

 

 

 

 

 

 

 

Date

17-12-2011

18-12-2011

19-12-2011

20-12-2011

21-12-2011

22-12-2011

23-12-2011

 

 

 

 

Nof labours

22

22

22

22

22

22

22

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Material Stocking Status

 

 

 

 

 

 

 

 

 

 

 

 

Required

Available

Remarks

 

 

 

 

 

 

 

 

Fine aggregate {cft}

300

400

 

 

 

 

 

 

 

 

 

Cement(bag)

300

275

 

 

 

 

 

 

 

 

 

Steel inT

7

9

 

 

 

 

 

 

 

 

 

Coarse Aggreagate (cft)

300

100

stock wil be replendished today

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Utility shifting

 

 

 

 

 

 

 

 

 

 

 

Utilities to be shifted

 

Remarks

 

 

 

 

 

 

 

 

 

BSNL

COMPLETED

 

 

 

 

 

 

 

 

 

 

KSEB

COMPLETED

 

 

 

 

 

 

 

 

 

 

KWA

COMPLETED

 

 

 

 

 

 

 

 

 

 

Others

COMPLETED

 

 

 

 

 

 

 

 

 

 
Back
 
    
METAL LAYING IN RE WALL PORTION

    
    
ROLLING OF SOIL IN 3RD LAYER OF RE WALL

    
    
FILLING OF SOIL USING JCB FOR RE WALL PORTION

    
    
PANEL ERECTION AT MC SIDE IN PROGRESS

    
 
    
RE WALL PANEL ERECTION OF 2ND LAYER

    
    
RC WALL CONCRETEING AT SHORNUR SIDE

    
    
PRECAST FOOT SLAB CASTING

    
 
    
METAL LEVELLING,SPREADING,ROLLING OF THE FIRST LAYER FOR REWALL

    
    
FILLIND AND LEVELLING OF SOIL FOR RE WALL

    
    
REINFORCEMENT FOR RETAINING WALL AT SHORNUR SIDE

    
 
 
 

 

 

 

 

 

 

 