   weekly progress 23.12.2011
    

 

Progress Report For Juliana  ROB for the week ending on 23.12.2011
Sl No   Activity Description   Total Quantity  Cumulative progress upto last week   Balance  work up to last week  Cumulative delay in Qty up to last week  Work  planned  during the week   Actual work done during the week   Cumulative delay in Qty up to this week  Work  Planned for next week   Remarks 
1 Pile towards NH side 26 26 0 0 0 0 0 0 TARGET ACHIEVED
2 Pile towards Puliyanam side 18 18 0 0 0 0 0 0 TARGET ACHIEVED
3 Pile cap at NH  Side 6 6 0 0 0 0 0 0 TARGET ACHIEVED
4 Pile Cap at Puliyanamside 4 4 0 0 0 0 0 0 TARGET ACHIEVED
5 RC wall at Puliyanam side 100% 70% 30% 0 0% 5% 0% 5%  
6 RC wall at NH side 100% 55% 45% 0 0% 10% 0% 10%  
7 Pier at NH Side 6 6 0 0 0 0 0 0 TARGET ACHIEVED
8 Pier at Puliyanam Side 4 4 0 0 0 0 0 0 TARGET ACHIEVED
9 Piercap at NH Side 6 5 1 0 0 0 0 1  
10 Piercap at Puliyanam 4 4 0 0 0 0 0 0 TARGET ACHIEVED
11 PEDESTAL 54 39 15 0 0 9 0 9  
12 Beam and cross beam at NH side 6 1 5 0 0 1 0 0  
13 Beam and cross beam at Puliyanam side  4 0 0 0 0 0 0 0   
 
Back
 
    
STAGING FOR SPAN P9-P10 19.12.2011

    
    
STAGING FOR SPAN P9-P10 19.12.2011

    
    
REINFORCEMENT WORK FOR PIER CAP P6

    
    
RC WALL PULIYANAM SIDE 19.12.2011

    
 
    
PULIANAM 23.12.2011BEAM P8-P9 CONCRETE 20.12.2011

      
 

 

 

 

 

 

 

 