Work Planned upto 30/01/2010 |
Completed / Progress |
Remarks |
P4-P5 Span Staging work |
Completed |
|
Concreting girders - 3 nos. |
Completed |
|
Arrangement for stressing girders |
In progress |
|
Approval of GAD by railways- follow up to be done by contractor |
|
Delay in GAD approval |
Box culvert works (under pass) |
Not started |
Delay by the contractor in starting under pass
|