   Weekly progress report as on 16.12.2011
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week 
1 PILE Muthambi side 27 18 9 0 0 0 0  
2 PILE Thamarassery side 33 24 9 0 5 3 0 6
3 PILE NH SIDE 30 20 10 0 5 2 0 2
4 PILE CAP Muthambi SIDE 9 5 4 0 0 1 0 1
4 PILE CAP Thamarassery SIDE 11 0 11 0 2 0 0 2
5 PILE CAP NH SIDE 10 0 10 0 2 0 0 2
6 PIER Muthambi  SIDE 9 5 4 0 1 2 0 1
7 PIER Thamarassery SIDE 11 0 11 0 0 0 0 0
8 PIER NH SIDE 10 0 10 0 1 0 0 1
9 PIER CAP Muthambi  SIDE 9 1 8 0 0 1 0 2
10 PIER CAP Thamarassery SIDE 11 0 11 0 0 0 0 0
11 PIER CAP NH SIDE 10 0 10 0 0 0 0 0
12 RE/R WALL Muthambi side 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%
13 RE/R WALL Thamarassery side SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%
14 RE/R WALL NH SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%
15 BEAM/SLAB Muthambi SIDE 8 0 8 0 0 0 0 0
16 BEAM/SLAB Thamarassery SIDE 10 0 10 0 0 0 0 0
17 BEAM/SLABNH SIDE 10 0 10 0 0 0 0 0
18 HR/FP/KERB Muthambi SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%
19 HR/FP/KERB thamarassery SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%
20 HR/FP/KERB NH SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%
21 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00% 

 

Availbility of Men               
Date 12-10-2011 12-11-2011 12-12-2011 13/12/2011 14/12/2011 15/12/2011 16/12/2011
Nof labours 55 55 55 55 55 55 55 

 

Material Stocking Status Required Available
Coarse Aggreagate (m3) 120 100
Fine Aggreagate(m3) 120 100
Cement(bag) 1400 1000
Steel(MT) 15 25 

 

 
Back
 
    
PILE LOAD TEST

    
    
P13,14&15 PIER COMPLETED

    
    
P12 PILECAP REINFORCEMENT WORK

    
    
P12 PIER SECOND LIFT CASTING

    
 
    
P12 PIER READY FOR CONCRETE

    
    
P10 PIER CASTING DONE

      
 

 

 

 

 

 

 

 