Prevoius Weekly Reports

   weekly progress 16.12.2011
    

   

SlNo  Activity –which can be completed without caution Total Quantity  Cumulative progress up to this week  Balance  work  Cumulative delay in weeks after  Work  planned  during the week  Actual work done during the last week  Short fall in the last week   Work   No of days remaining for completion as per the weekly plan Remarks 
Description  -1 -2 Spplagmnt  -4 -5 -6 Planned for next week 
      -3       -7
1 Re wall towards NH side  100% 34 66 32     0 0  0  .
3 Approach  5 5 0 37     
 Span
4 Pier cap  2 2 0 46  0   0   0   0   0   
5 Pile (Rly)pulikakadavu side  4 4 0 60  0  0   0    0  0  
6 Pile (Rly)Nh side 4 4 0 60 0 0 0 0 0  
6 Piers (Rly) 2 2 0 51  0   0   0   0     
9 R0AD WORK 100% 90 0                  
{WBM} towards pulikkakadavu side
                       
1O Kerb/handrail  (approach portion)N.H side 200m Inner kerb concreting complete for a distance of  25 metres.Handrail posts  concreted for a. distance of 50 metres.No work in the last week.   Nil            
12 Friction slab  approach portion(N.H side 200m No work in the last week                     
 
 
Back
 
    
CONCRETING OF THE TRESTLE BEAM AT P8

    
    
CURING AT P8 TRESTLE BEAM

    
    
CURING AT P8 TRESTLE BEAM

    
    
DESHUTTERING OF THE TRESTLE BEAM

    
 
    
CONCRETING OF THE TRESTLE BEAM AT P8 LOCATION.

      
 

 

 

 

 

 

 

 