Untitled Document
Road to Prosperity
Site last updated on: 12-12-2020 | You are visitor:
8053473
Contact Us
Login
Home
About Us
Vision
Profile
Board of Directors
Organization Chart
Staff Profile
Articles Of Association
Projects
At a Glance
Completed Projects
Projects Under Construction
Tendering stage
Land Acquisition in Progress
DPR under KIIFB review
DPR under preparation
Toll Collection
KIIFB Projects
Acts & Rules
Right to Information
Tenders
Corporate Governance
Annual Accounts
Annual Reports
Photo Gallery
Completed Projects
Projects Under Construction
Citizen Services
Careers
Right to Service
Prevoius Weekly Reports
Weekly progress report as on 16.12.2011
Service road on kanjippuram side
Completed
for piling.
Piling
In progress
Completed 30 nos (P11-3, P12-3,P17-3,P19-3,P13-3, P18-3,AP2-3, P14-3, P15-3 P16-3)
Pile cap
In progress
Completed 2 nos(P11,P12)
Reinforcement for Pile cap P11
completed
Load testing for P19 a
In progress
Back
PILE LOAD TEST AT P 19 A
PILE CAP AT P12
PILE CAP AT P12
PILE CAP AT P11