   weekly progress 16.12.2011
    

 

Revised Progress Report For Ponnurunni ROB for the week ending on 15.12.11
Si No  Activity Description  Total Quantity Cumulative progress upto 15.12.11 Balance  work up to 15.12.11 Cumulative delay in Qty up to 15.12.11 Work  planned  during the week  Actual work done during the week  delay in Qty up to this week Work  Planned for next week 
1 PILE  Palarivattom side(Approach portion) 31 28 3 0 0 0 0 0
2 PILE Palarivattom side(railway portion) 6 0 6 0 0 0 0 0
3 PILE vytilla side(Approach portion) 42 0 42 0 0 0 0 0
4 PILE vytilla side(railway portion) 6 0 6 0 0 0 0 0
5 PILE CAP Palarivattom side(Approach portion) 8 7 1 1 1 1 0 0
6 PILE CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0
7 PILE CAP vytilla side(Approach portion) 9 0 9 0 0 0 0 0
8 PILE CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0
9 PIER Palarivattom side(Approach portion) 8 7 1 0 3 1 0 0
10 PIER Palarivattomside(railway portion) 1 0 1 0 0 0 0 0
11 PIER Vytilla side(Approach portion) 9 0 9 0 0 0 0 0
12 PIER vytilla side(railway portion) 1 0 1 0 0 0 0 0
13 PIER  CAP Palarivattom side(Approach portion) 8 7 1 0 0 0 2 2
14 GIRDER Palarivattom side(Approach portion) 7 3 4 0 1 1 0 0
15 PIER CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0
16 PIER CAP  Vytilla side(Approach portion) 9 0 9 0 0 0 0 0
17 PIER CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0
18 RE WALL PANEL 355 355 0 0 0 1 0 0
  Labour Report                
                   
  Date 09.12.11 10.12.11 11.12.11 12.12.11 13.12.11 14.12.11 15.12.11  
  Day Fri Sat Sun Mon Tue Wed Thurs  
  Climate sunny  sunny  sunny  sunny  sunny  sunny  sunny   
  No.of labours 34 33 24 12 (lbr strike) 39 35 41  
  Availability of Material                 
                   
  Materials Required for week ending on 22.12.11 Available as on 15.12.11            
  Fine aggregate(M3) Ready Mix Concrete            
  Coarse aggregate(M3)            
  Cement(BAG)            
  Steel(TONN) 0 57            
 
Back
 
    
DIAPHRAM A2

    
    
MS SHEETS AT RP1

    
    
A2 P15 DIAPHRAGM CONCRETING

    
    
REINFORCEMENT P13 P12 GIRDER

    
 
    
TRIPOD ERECTION AT RP1.

    
    
TRIPOD ERECTION P4

      
 

 

 

 

 

 

 

 