Revised Progress Report For Ponnurunni ROB for the week ending on 15.12.11 |
Si No |
Activity Description |
Total Quantity |
Cumulative progress upto 15.12.11 |
Balance work up to 15.12.11 |
Cumulative delay in Qty up to 15.12.11 |
Work planned during the week |
Actual work done during the week |
delay in Qty up to this week |
Work Planned for next week |
1 |
PILE Palarivattom side(Approach portion) |
31 |
28 |
3 |
0 |
0 |
0 |
0 |
0 |
2 |
PILE Palarivattom side(railway portion) |
6 |
0 |
6 |
0 |
0 |
0 |
0 |
0 |
3 |
PILE vytilla side(Approach portion) |
42 |
0 |
42 |
0 |
0 |
0 |
0 |
0 |
4 |
PILE vytilla side(railway portion) |
6 |
0 |
6 |
0 |
0 |
0 |
0 |
0 |
5 |
PILE CAP Palarivattom side(Approach portion) |
8 |
7 |
1 |
1 |
1 |
1 |
0 |
0 |
6 |
PILE CAP Palarivattomside(railway portion) |
1 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
7 |
PILE CAP vytilla side(Approach portion) |
9 |
0 |
9 |
0 |
0 |
0 |
0 |
0 |
8 |
PILE CAP vytilla side(railway portion) |
1 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
9 |
PIER Palarivattom side(Approach portion) |
8 |
7 |
1 |
0 |
3 |
1 |
0 |
0 |
10 |
PIER Palarivattomside(railway portion) |
1 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
11 |
PIER Vytilla side(Approach portion) |
9 |
0 |
9 |
0 |
0 |
0 |
0 |
0 |
12 |
PIER vytilla side(railway portion) |
1 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
13 |
PIER CAP Palarivattom side(Approach portion) |
8 |
7 |
1 |
0 |
0 |
0 |
2 |
2 |
14 |
GIRDER Palarivattom side(Approach portion) |
7 |
3 |
4 |
0 |
1 |
1 |
0 |
0 |
15 |
PIER CAP Palarivattomside(railway portion) |
1 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
16 |
PIER CAP Vytilla side(Approach portion) |
9 |
0 |
9 |
0 |
0 |
0 |
0 |
0 |
17 |
PIER CAP vytilla side(railway portion) |
1 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
18 |
RE WALL PANEL |
355 |
355 |
0 |
0 |
0 |
1 |
0 |
0 |
|
Labour Report |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Date |
09.12.11 |
10.12.11 |
11.12.11 |
12.12.11 |
13.12.11 |
14.12.11 |
15.12.11 |
|
|
Day |
Fri |
Sat |
Sun |
Mon |
Tue |
Wed |
Thurs |
|
|
Climate |
sunny |
sunny |
sunny |
sunny |
sunny |
sunny |
sunny |
|
|
No.of labours |
34 |
33 |
24 |
12 (lbr strike) |
39 |
35 |
41 |
|
|
Availability of Material |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Materials |
Required for week ending on 22.12.11 |
Available as on 15.12.11 |
|
|
|
|
|
|
|
Fine aggregate(M3) |
Ready Mix Concrete |
|
|
|
|
|
|
|
Coarse aggregate(M3) |
|
|
|
|
|
|
|
Cement(BAG) |
|
|
|
|
|
|
|
Steel(TONN) |
0 |
57 |
|
|
|
|
|
|