Progress Report For Pulianam  ROB for the week ending on16.12..2011 
Sl No   Activity Description   Total Quantity  Cumulative progress upto last week   Balance  work up to last week  Cumulative delay in Qty up to last week  Work  planned  during the week   Actual work done during the week   Cumulative delay in Qty up to this week  Work  Planned for next week   Remarks 
1 Pile towards NH side 26 26 0 0 0 0 0 0 TARGET ACHIEVED
2 Pile towards Puliyanam side 18 18 0 0 0 0 0 0 TARGET ACHIEVED
3 Pile cap at NH  Side 6 6 0 0 0 0 0 0 TARGET ACHIEVED
4 Pile Cap at Pulianam side 4 4 0 0 0 0 0 0 TARGET ACHIEVED
5 RC wall at Puliyanam side 100% 65% 35% 0 0% 10% 0% 10%  
6 RC wall at NH side 100% 45% 55% 0 0% 10% 0% 10%  
7 Pier at NH Side 6 6 0 0 0 0 0 0 TARGET ACHIEVED
8 Pier at Puliyanam Side 4 4 0 0 0 0 0 0 TARGET ACHIEVED
9 Piercap at NH Side 6 5 1 0 0 0 0 1  
10 Piercap at Puliyanam 4 4 0 0 0 0 0 0 TARGET ACHIEVED
11 PEDESTAL 60 30 30 0 6 6 0 12  
                     
Date 10.12.11 12.12.11 13.12.11 14.12.11 15.12.11 16.12.11        
Climate pleasant pleasant pleasant pleasant pleasant pleasant        
No.of labours 60 60 61 59 59 61        
                     
availability of material                  
materials Required Available                
Fine aggregate(M3) 15 18                
Coarse aggregate(M3) 17 22                
Cement(BAG) 500 850                
Steel(TONN) 4.5 60                
 