   Weekly progress report as on 09.12.2011
    
 

Description

Completed/ Progress

Remarks

Pier cap (Total no of pier Cap- 21)

Completed

21 NOS COMPLETED

RE Wall panel casting ( total600 nos)

Completed

 

Slab calicut side  (total 10 nos )

In progress

9nos done  (adjacent span pending )

slab NH side ( 11 nos)

In progress

10nos done  (adjacent span pending )

Retaining wall NH side

In progress

Done LHS -90%, RHS- 90%

Dirt wall AP2 concreting

In progress

Done 90%

Dirt wall AP1 concreting

In progress

Done 90%

Handrail casting

In progress

1000 nos completed.

Handrail fixing

In progress

NH side 10 slab completed.

Boring at RP4

In progress

RP-4 THREE pile concreted.boaring in progress.

Boring at RP1

In progress

ONE pile concreted

NH side RE panel erection

In progress

70% completed.

RE wall excavation Calicut side

Completed

Foundation design should summit by contractor.

expansion joint NH side completed

Completed

9 nos completed.

expansion joint calicut  side completed

Completed

8 noscompleted. 

 

 
Back
 
    
RE WALL WORK NH SIDE.

    
    
PILE CONCRETING IN RP4-P2.

    
    
HANDRAIL WORK IN NH-SIDE.

    
    
BOARING IN RP4-P1.

    
 
    
BOARING IN RP1-2P.

      
 

 

 

 

 

 

 

 