   Weekly prgoress report as on 09.12.2011
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PILE CHERUVATHOOR  SIDE

27

21

6

2

0

0

0

0

 

 

2

PILE PADANNA SIDE

24

15

9

2

3

2

5

2

 

 

3

PILE CAP CHERUVATHOOR SIDE

9

6

3

1

1

0

1

1

 

 

4

PILE CAP  PADANNA SIDE

8

2

6

0

2

2

0

1

 

 

5

PIER CHERUVATHOOR SIDE

9

3

6

0

2

2

0

0

 

 

6

PIER PADANNA SIDE

8

0

8

0

0

0

0

2

 

 

7

PIER CAP CHERUVATHOOR SIDE

9

3

6

0

0

0

0

2

 

 

8

PIER CAP PADANNA SIDE

8

0

8

0

0

0

0

0

 

 

9

RE/R WALL CHERUVATHOOR  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

RE panel casting to start this week

10

RE/R WALL PADANNA SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

11

BEAM/SLAB CHERUVATHOOR  SIDE

9

0

9

0

0

0

0

0

 

reinforcement and shuttering  for AP2-P15 girder in progress

12

BEAM/SLAB PADANNA SIDE

8

0

8

0

0

0

0

0

 

 

13

HR/FP/KERB CHERUVATHOOR  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

14

HR/FP/KERB PADANNA SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

15

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

  

 

Availbility of Men               
Date 03-12-2011 04-12-2011 05-12-2011 06-12-2011 07-12-2011 08-12-2011 09-12-2011
Nof labours 29 51 51 51 51 51 51 

 

Material Stocking Status Required Available
Coarse Aggreagate (m3) available  
Fine Aggreagate(m3) available  
Cement(bag) 500 590
Steel(MT) 15 50 

 

Utility shifting        
Utilities to be shifted Status Remarks    
BSNL AP1,P9,P10 to be shifted.P10 shifting in progress
KSEB in progress estimation yet to be received,P1 location cleared.
KWA currently can be managed at site       
Others         

 

 

AREAS OF  CONCERN AND CORRECTIVE ACTION:

 

 

 

 

 

 

 

1

Water logging at P11 . Bunds in progress ,pumping out water in progress .

 

2

Land acquisition at AP1(BSNL) not yet done.At Padanna side, no workfront after PI location .P9 building demolition to start soon.

3

Winch breakdown for 10 days:winch repaired on 24-11-11

 

 

 

 

 

 

 

 

 
Back
 
    
P14 PIER CONCRETE COMPLETE

    
    
P12 PIER COMPLETE

    
    
P11 LOCATION

    
    
P3 PILE CAP CONCRET

    
 
    
BORING IN PROGRESS AT P4 C

    
    
AP2-P15 GIRDER REINF IP

      
 

 

 

 

 

 

 

 