Prevoius Weekly Reports

   Weekly progress report as on 09.12.2011
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

1

PILE THRIKKARIPUR  SIDE

33

33

Completed

2

PILE EZHIMALA SIDE

27

27

Completed

3

PILE PAYYANNUR SIDE

27

27

Completed

4

PILE CAP THRIKKARIPUR  SIDE

11

11

Completed

5

PILE CAP EZHIMALA SIDE

9

9

Completed

6

PILE CAP PAYYANNUR SIDE

9

9

Completed

9

PIER THRIKKARIPUR  SIDE

11

11

Completed

8

PIER EZHIMALA SIDE

9

9

Completed

9

PIER PAYYANNUR SIDE

9

9

Completed

10

PIER CAP THRIKKARIPUR  SIDE

11

11

Completed

11

PIER CAP EZHIMALA SIDE

9

9

Completed

12

PIER CAP PAYYANNUR SIDE

9

9

Completed

16

RE/R WALL THRIKKARIPUR  SIDE

100%

65%

35%

0

10.00%

10.00%

5.00%

10.00%

17

RE/R WALL EZHIMALA SIDE

100%

55%

45%

0

5.00%

5.00%

0.00%

5.00%

18

RE/R WALL PAYYANNUR SIDE

100%

10

90%

0

0.00%

0.00%

0.00%

0.00%

28

BEAM/SLAB THRIKKARIPUR  SIDE

10

10

0

0

0

0

0

0

29

BEAM/SLAB EZHIMALA SIDE

7

7

0

0

0

0

0

0

30

BEAM/SLAB PAYYANNUR SIDE

10

8

2

2

0

0

2

0

31

HR/FP/KERB THRIKKARIPUR  SIDE

100%

85%

15%

15%

0.00%

10.00%

0.00%

30.00%

32

HR/FP/KERB EZHIMALA SIDE

100%

70%

30%

30%

10.00%

10.00%

0.00%

0.00%

33

HR/FP/KERB PAYYANNUR SIDE

100%

100%

0%

0

40.00%

40.00%

0.00%

0.00%

34

BC/PAINTING

100%

0.04

96%

0

2.40%

2.40%

0.00%

3.00% 

 

Availbility of Men

 

 

 

 

 

 

 

 

Date

02-12-2011

03-12-2011

04-12-2011

05-12-2011

06-12-2011

07-12-2011

08-12-2011

09-12-2011

Nof labours

48

48

48

48

46

46

44

50 

 

Material Stocking Status Required Available
Coarse Aggreagate (m3) available  
Fine Aggreagate(m3) available  
Cement(bag) 300 500
Steel(MT) 5 20
      

 

Utility shifting  
Utilities to be shifted Status
BSNL completed
KSEB completed
KWA completed
Others completed 

 

Description Progress/Completed Remarks
Pier cap concreting (Total no of pier cap- 29) completed  
Slab  Thrikkaripur side (  10 nos) completed 10 nos done
Slab Ezhimala side ( 7 nos) completed 7nos done
Slab Payyanur side ( 10 nos) Remaining two can be done
only after railway portion is done
8 nos done
Retaining wall/RE wall panel casting- Ezhimala side In progress done 65%
Retaining wall Thrikkaripur side (RHS) In progress Done 85%
Handrail & Kerb payyannur side completed  
Handrail & Kerb Thrikaripur side In progress AP1-1-2-3-4-5-6-7-8 completed
Handrail & Kerb Ezhimala side In progress P9-10-11,13-14-15-16-AP2
Expansion joint: Payyannur side completed 1 LEFT
Expansion joint: Ezhimala side In progress 1 LEFT
Expansion joint: Thrikkarippur side In progress 1 LEFT
Kerb completed (total 25 spans complete)
Painting  In progress Payyannur side 6 spans completed 

 

 
Back
 
    
PNR RE WORKS IP

    
    
PAINTING IP AT PNR SIDE

    
    
HANDRAIL WORKS FINISHING IP

    
    
EZHIMALA SIDE FRICTION SLAB IP

    
 
 
 

 

 

 

 

 

 

 