   Weekly progress report as on 09.12.2011
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PILE SHORNUR  SIDE

9

9

 

 

 

Completed

 

 

 

2

PILE M.C SIDE

36

36

 

 

 

Completed

 

 

 

 

3

PILE CAP SHORNUR SIDE

3

3

 

 

 

Completed

 

 

 

 

4

PILE CAP  M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

5

PIER SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

 

6

PIER M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

7

PIER CAP SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

 

8

PIER CAP M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

9

RE/R WALL SHORNUR SIDE

100%

48

52%

0

15.00%

3.00%

63.00%

20.00%

0

Concreting of RCC retaining wall (complete 1 side).Reinforcement work for the raft and RCC wall in progress on the other side.

10

RE/R WALL M.C SIDE

100%

9

91%

0

5.00%

1.00%

13.00%

15.00%

0

Compactio work for the RE panel casting in progress.Erection of the first layer of RE panel work is to start today.

11

BEAM/SLAB SHORNUR  SIDE

3

2

1

0

0

0

0

0

0

 

12

BEAM/SLAB M.C SIDE

12

11

1

0

1

1

0

0

0

deshuttering of the span P3-P4 completed.Therefore deshuttering work of all spans (beam and deck slab) completed..

13

HR/FP/KERB SHORNUR  SIDE

100%

62

38%

0

0.00%

0.00%

0.00%

0.00%

0 days

Concreting of the inner kerb at span AP1-P1 completed.Therefore concreting of inner kerb of all the spans completed.

14

HR/FP/KERB M.C SIDE

100%

53

47%

0

8.00%

1.00%

6.00%

8.00%

 

Expansion joint works   at locations P4 work completed.Footpath slab concreting completed for spans P6-P7,P9-P8 completed.

15

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

  

 

Availbility of Men               
Date 12-03-2011 12-04-2011 12-05-2011 12-06-2011 7-12-2011. 12-08-2011 12-09-2011
Nof labours 14 14 12 14 14 14 14 

 

Material Stocking Status          
  Required Available Remarks    
Fine aggregate {cft} 300 250 stock wil be replendished today    
Cement(bag) 450 160 stock replendished only today    
Steel inT 7.5 8      
Coarse Aggreagate (cft) 300 400      

 

Utility shifting  
Utilities to be shifted  
BSNL COMPLETED
KSEB COMPLETED
KWA COMPLETED
Others COMPLETED 

 

 