Prevoius Weekly Reports

   Weekly progress report as on 09.12.2011
    
 

Sl No 

Activity Description 

Total Quantity

Cumulative progress upto last week 

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week 

Actual work done during the week 

Cumulative delay in Qty up to this week

Work  Planned for next week 

Remarks

1

Pile towards NH side

26

26

0

0

0

0

0

0

TARGET ACHIEVED

2

Pile towards Puliyanam side

18

18

0

0

0

0

0

0

TARGET ACHIEVED

3

Pile cap at NH  Side

6

6

0

0

0

0

0

0

TARGET ACHIEVED

4

Pile Cap at Pulianam side

4

4

0

0

0

0

0

0

TARGET ACHIEVED

5

RC wall at Puliyanam side

100%

55%

44%

0

0%

10%

0%

10%

 

6

RC wall at NH side

100%

35%

65%

0

0%

10%

0%

10%

 

7

Pier at NH Side

6

6

0

0

0

0

0

0

TARGET ACHIEVED

8

Pier at Puliyanam Side

4

4

0

0

0

1

0

0

TARGET ACHIEVED

9

Piercap at NH Side

6

5

1

0

0

0

0

1

 

10

Piercap at Puliyanam

4

4

0

0

0

0

0

0

TARGET ACHIEVED

11

PEDESTAL

60

24

36

0

6

0

0

12

  

 

Labour & Climate details

Date

 

3.12.11

 

6.12.11

 

7.12.11

 

8.12.11

 

9.12.11

Climate pleasant pleasant pleasant pleasant pleasant
No.of labours 55 55 55 58 58
           
availability of material        
materials Required Available      
Fine aggregate(M3) 10 12      
Coarse aggregate(M3) 14 22      
Cement(BAG) 500 850      
Steel(TONN) 4.5 60      

 

 

 
Back
 
    
RC WALL PULIYANAM SIDE -CONCRETE

    
    
RC WALL NH SIDE -CONCRETE

    
    
PIER P6 4TH LIFT

      
 

 

 

 

 

 

 

 