   Weekly progress report as on 02.12.2011
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE  CALICUT  SIDE 48 48 0 0 4 4 1 4    
2 PILE THIRUR SIDE 24 10 14 0 4 2 2 4    
3 PILE CAP CALICUT  SIDE 12 11 1 0 1 0 1 1    
4 PILE CAP  THIRURSIDE 6 0 6 0 0 0 0 0    
5 PIER CALICUT SIDE 12 11 1 0 2 2 0 1    
6 PIER THIRUR SIDE 6 0 6 0 0 0 0 0    
7 PIER CAPCALICUT   SIDE 12 3 9 0 1 1 0 1   staging @ p8 completed
8 PIER CAP THIRUR SIDE 6 0 6 0 0 0 0 0    
9 RE/R WALL CALICUT   SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
10 RE/R WALLTHIRUR SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
11 BEAM/SLAB CALICUT   SIDE 12 0 12 0 0 0 0 0    
12 BEAM/SLAB THIRUR SIDE 6 0 6 0 0 0 0 0    
13 HR/FP/KERB CALICUT   SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
14 HR/FP/KERBTHIRUR SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%     

 

Availbility of Men             
Date 26-11-2011 27-11-2011 28-11-2011 29-11-2011 30-10-2011 01-12-2011 02-12-2011
Nof labours 42 42 42 42 42 42 42 

 

Material Stocking Status Required Available
Coarse Aggreagate (m3) 28 21
Fine Aggreagate(m3) 18 10
Cement(bag) 450 190
Steel(MT)

 

Utility shifting

 
Utilities to be shifted Status
BSNL shifting completed
KSEB shifting in progress
KWA shifting completed 
  16 

 

 

 
Back
 
    
REINFORCEMENT @ ABUTMENT1 PILECAP

    
    
CONCRETE@ P14

    
    
BORING GOIN ON @ P14 & P15

    
    
BORING @ P14

    
 
    
BORIN @ P14

      
 

 

 

 

 

 

 

 