Work Planned upto 6/02/2010 |
Completed / Progress |
Remarks |
P4-P5 Span Staging work |
Completed |
|
Concreting girders - 3 nos. |
Completed |
|
Stressing girders |
Completed |
|
Shuttering work for cross beam & slab |
In progress |
|
Approval of GAD by railways- follow up to be done by contractor |
|
Delay in GAD approval.Road to be blocked for taking P3-P4 span work |
Box culvert works (under pass) |
Not started |
Delay by the contractor in starting under pass |