Description |
Progress/Completed |
Remarks |
|
Staging drawing approval from Railways |
pending |
1 no yet to be received (RP3-RP4) |
|
Fabrication works for railway staging for Bowsrting |
Completed |
|
|
Retaining wall (Palakkad side) |
In progress |
90% work done |
|
Kerb Casting (Palakkad side) |
In progress |
65% completed |
|
Drain work Retaining wall (Moyan school side) |
In progress |
done 15% |
|
Retaining wall (Moyan school side) |
In progress |
100% completed |
|
Kerb Casting (Moyens side) |
In progress |
100% completed |
|
Bowstring girder |
In progress |
Suspenders casting completed |
|
Bow arch beam |
In progress |
Barbending and shuttering in progress |
|
Casting of Bow arch bem |
In progress |
25% completed |
|
Handrail fixing & kerb casting |
In progress |
4 slabs of Moyen's side and 2 slabs of Pkd side completed. |
|
Bowstring girder Stressing and grouting |
Completed |
|
|
RP6-RP7-RP8 railway slab |
Completed |
|
|
RP7-P5, P5-P6, P6-P7, P7-P8 Deck slab and girder |
completed |
Moyen's school side deck slabs |
|
P1-P2, P4-RP1 Deck slabs and girder |
Completed |
Pkd side deck slabs |
|
RP5-RP6 girders |
In progress |
4 No.s girder casting completed |
|
RP5-RP6 deck slab work |
In progress |
Casting completed |
|
Approach filling |
In progress |
Moyen's school side & Pkd side |
|
Cantilver portion of P7-P8 & P1-P2 |
completed |
|