Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7888614
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 02.12.2011
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week 
1 PCC for RAFT MOYAN SIDE 3 3 0 0 0 0 0 0
2 PCC for RAFT PALAKKAD SCHOOL SIDE 1 1 0 0 0 0 0 0
3 RAFT PALAKKAD SIDE 1 1 0 0 0 0 0 0
4 RAFT MOYAN SCHOOL SIDE 3 3 0 0 0 0 0 0
5 PIER PALAKKAD SIDE 1 1 0 0 0 0 0 0
6 PIER MOYAN SCHOOL SIDE 3 3 0 0 0 0 0 0
7 PIER CAP PALAKKAD SIDE 1 1 0 0 0 0 0 0
8 PIER CAP MOYAN SCHOOL SIDE 3 3 0 0 0 0 0 0
9 RE/R WALL PALAKKAD  SIDE 100% 75% 25% 0 0.00% 0.00% 0.00% 0.00%
10 RE/R WALL MOYAN SCHOOL SIDE 100% 70% 30% 0 0.00% 0.00% 0.00% 5.00%
11 BEAM/SLAB  Staging Palakad  SIDE 2 2 0 0 0 0 0 0
12 BEAM/SLAB  Bar bending and Fixing Palakad  SIDE 2 2 0 0 0 0 0 0
13 BEAM/SLAB  Shuttering  and Concreting Palakad SIDE 2 2 0 0 0 0 0 o
14 BEAM/SLAB  Staging Moyan schoolSIDE 4 4 0 0 0 0 0 0
15 BEAM/SLAB  Bar bending and Fixing Moyan school SIDE 4 4 0 0 0 0 0 0
16 BEAM/SLAB  Shuttering  and Concreting  Moyan school  SIDE 4 4 0 0 0 0 0 0
17 BEAM/SLAB PALAKKAD  SIDE 2 2 0 0 0 0 0 0
18 BEAM/SLAB MOYAN SCHOOL SIDE 4 4 0 0 0 0 0 0
19 BEAM/SLAB RAILWAY SPAN 7 3 4 0 0 0 0 0
20 HR/FP/KERB Pkd  SIDE 100% 75% 25% 0 0.00% 0.00% 0.00% 10.00%
21 HR/FP/KERB Moyen's SIDE 100% 100% 0% 0 0.00% 30.00% 0.00% 0.00%
22 HR/FP/KERB RAILWAY SPAN 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%
23 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00% 

 

Description Progress/Completed Remarks
Staging drawing approval from Railways pending 1 no yet to be received (RP3-RP4) 
Fabrication works for railway staging for Bowsrting Completed  
Retaining wall (Palakkad side)  In progress 90% work done
Kerb Casting (Palakkad side) In progress 65% completed
Drain work Retaining wall (Moyan school  side)  In progress done 15%
Retaining wall (Moyan school  side)  In progress 100% completed
Kerb Casting (Moyens side) In progress 100% completed
Bowstring girder In progress Suspenders casting completed
Bow arch beam In progress Barbending and shuttering in progress
Casting of Bow arch bem In progress 25% completed
Handrail fixing & kerb casting In progress 4 slabs of Moyen's side and 2 slabs of Pkd side completed.
Bowstring girder Stressing and grouting Completed  
RP6-RP7-RP8 railway slab Completed  
RP7-P5, P5-P6, P6-P7, P7-P8 Deck slab and girder completed Moyen's school side deck slabs
P1-P2, P4-RP1 Deck slabs and girder Completed Pkd side deck slabs
RP5-RP6 girders In progress 4 No.s girder casting completed
RP5-RP6 deck slab work In progress Casting completed
Approach filling In progress Moyen's school side & Pkd side
Cantilver portion of P7-P8 & P1-P2 completed   

 

 

 
Back
 
    
CASTING OF BOWSTRING ARCH BEAM

    
    
BARBENDING OF ARCH BEAM

    
    
ARCH BEAM STEEL WORK

    
    
APPROACH KERB

    
 
    
APPROACH FILLING

      
 

 

 

 

 

 

 

 

Untitled Document