   Weekly progress report as on 02.12.2011
    
Sl No  Activity Description  Total Quantity Cumulative progress upto 01.12.11 Balance  work up to 01.12.11 Cumulative delay in Qty up to 01.12.11 Work  planned  during the week  Actual work done during the week  Delay in Qty up to this week Work  Planned for next week 
1 PILE  Pettah side(Approach portion) 12 6 6 3 4 3 3 4
2 PILE Anayara side(Approach portion) 12   12          
3 PILE CAP Pettah side(Approach portion) 4   4          
4 PILE CAP Anayara side(Approach portion) 4   4          
5 PIER Pettah side(Approach portion) 4   4          
6 PIER Anayara side(Approach portion) 4   4          
7 PIER  CAP Pettah side(Approach portion) 4   4          
8 GIRDER Pettah side(Approach portion) 4   4          
9 GIRDER Anayara side(Approach portion) 4   4          
10 Service Road Pettah side(Approach portion) 1400 350 1050          
11 Service Road Anayara side(Approach portion) 1400 350 1050           

 

 