Description |
Completed/ Progress |
Remarks |
Pier cap (Total no of pier Cap- 21) |
Completed |
21 NOS COMPLETED |
RE Wall panel casting ( total 550 nos) |
Completed |
|
Slab calicut side (total 10 nos ) |
In progress |
9nos done (adjacent span pending ) |
slab NH side ( 11 nos) |
In progress |
10nos done (adjacent span pending ) |
Retaining wall NH side |
In progress |
Done LHS -90%, RHS- 90% |
Dirt wall AP2 concreting |
In progress |
Done 90% |
Dirt wall AP1 concreting |
In progress |
Done 90% |
Handrail casting |
In progress |
1000 nos completed. |
Handrail fixing |
In progress |
NH side 9 slab completed. |
Boring at RP4 |
In progress |
RP-4 two pile concreted.boaring in progress. |
Boring at RP1 |
In progress |
boaring in progress. |
NH side RE panel erection |
In progress |
60% completed. |
RE wall excavation Calicut side |
Completed |
Foundation design should summit by contractor. |
expansion joint NH side completed |
Completed |
9 nos completed. |
expansion joint calicut side completed |
Completed |
8 nos completed. |