|
Prevoius Weekly Reports
|
Weekly progress report as on 02.12.2011 |
|
DESCRIPTION |
Completed/Progress |
Remarks |
Service road on kanjippuram side |
Completed |
for piling. |
Piling |
In progress |
29 nos (P11-3, P12-3,P17-3,P19-3,P13-3, P18-3,AP2-3, P14-3, P15-2 P16-3) |
Pile cap excavation for P11 |
In progress |
|
|
|
|
Back |
|
PILE P15 A
|
| | |
PILE 15 B
|
| | |
PILE 15 B
|
| | |
PILE 15 A
|
| | |
|
PILE 14B
|
| | |
|
|
|