Weekly progress report as on 02.12.2011 |
| |
|
DESCRIPTION |
Completed/Progress |
Remarks |
|
Service road on kanjippuram side |
Completed |
for piling. |
|
Piling |
In progress |
29 nos (P11-3, P12-3,P17-3,P19-3,P13-3, P18-3,AP2-3, P14-3, P15-2 P16-3) |
|
Pile cap excavation for P11 |
In progress |
|
|
|
| |