Description |
Progress/Completed |
Remarks |
Pile concreting |
in progress |
Done 36os |
Pile cap |
in progress |
Done 7 nos (P12 and P14 done this week) |
Pier |
in progress |
Done 3 nos-AP2,P15 and P13 |
Pier beam |
in progress |
3 done-AP2,P15,P14 |
Staging for girder at AP2-P15 |
in progress |
|
Building demolition at P2,P3 location |
completed |
|
building demolition at P4 location |
completed |
|
Demolition of 2 shops in P6 location |
Completed |
|
Building demolition near P8 location |
In progress |
|
Pile load test at P7 b |
completed |
|
Site clearing at pile load test area |
in progress |
Excavation and pile chipping complete |
Site clearing |
In progress |
P1,P2,P3,P4,P5 locations site clearing complete,ROAD diversion complete at Padanna side |
P4 location electric line shifting |
completed |
|
Pile chipping |
completed |
at P3,P2,P7locations |