   Weekly progress report as on 02.12.2011
    

 

Sl No 
Activity Description 
Total Quantity
Cumulative progress upto last week 
Balance work up to last week
Cumulative delay in Qty up to last week
Work  planned  during the week 
Actual work done during the week 
Cumulative delay in Qty up to this week
Work  Planned for next week 
Remarks
1
Pile towards NH side
26
26
0
0
0
0
0
0
TARGET ACHIEVED
2
Pile towards Puliyanam side
18
18
0
0
1
1
0
0
TARGET ACHIEVED
3
Pile cap at NH  Side
6
6
0
0
0
0
0
0
TARGET ACHIEVED
4
Pile Cap at Pulianam side
4
4
0
0
0
0
0
0
TARGET ACHIEVED
5
RC wall at Puliyanam side
100%
45%
55%
0
0%
5%
0%
5%
 
6
RC wall at NH side
100%
25%
75%
0
0%
5%
0%
5%
 
7
Pier at NH Side
6
5
1
0
0
0
0
1
 
8
Pier at Puliyanam Side
4
4
0
0
0
0
0
0
TARGET ACHIEVED
9
Piercap at NH Side
6
5
1
0
0
0
0
1
 
10
Piercap at Puliyanam
4
4
0
0
0
0
0
0
TARGET ACHIEVED
11
PEDESTAL
60
24
36
0
6
6
0
12
 

 

 

 

 

 

 

 

 

 

 

 

Date
26.11.11
28.11.11
30.11.11
1.12.11
2.11.11

 

 

 

 

 

Climate
pleasant
pleasant
pleasant
pleasant
pleasant

 

 

 

 

 

No.of labours
39
55
56
55
56

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

availability of material

 

 

 

 

 

 

 

 

 

materials
Required
Available

 

 

 

 

 

 

 

 

Fine aggregate(M3)
8
11

 

 

 

 

 

 

 

 

Coarse aggregate(M3)
14
22

 

 

 

 

 

 

 

 

Cement(BAG)
250
550

 

 

 

 

 

 

 

 

Steel(TONN)
3.5
60

 

 

 

 

 

 

 

 

 
Back
 
    
STEEL WORK FOR BEAM (P8-P9) 30.11.11

    
    
SPAN P8-P9 28.11.11

    
    
RC WALL NH SIDE BASE SLAB, CONCRETE 2.12.11

    
    
PIER P6 3RD LIFT CONCRETE 2.12.11

    
 
 
 

 

 

 

 

 

 

 