   Weekly progress report as on 02.12.2011
    

 

 

Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE KAINATTY  SIDE 18 18 0 0 0 0 0 0    
2 PILE NADAPURAM SIDE 27 27 0 0 0 0 0 0    
3 PILE CAP KAINATTY SIDE 6 5 1 1 0 0 1 0    
4 PILE CAP  NADAPURAM SIDE 9 9 0 0 0 0 0 0    
  PIER KAINATTY  SIDE 6 5 1 1 0 0 1 0    
6 PIER NADAPURAM SIDE 9 9 0 0 0 0 0 0    
7 PIER CAP KAINATTY  SIDE 6 5 1 1 0 0 1 0    
8 PIER CAP NADAPURAM SIDE 9 8 1 1 0 0 1 0    
11 RE/R WALL KAINATTY  SIDE 100% 0% 100% 0 0.00% 0.00% 0.00% 0.00%    
10 RE/R WALL NADAPURAM SIDE 100% 15% 85% 0 0.00% 0.00% 0.00% 0.00%    
12 BEAM/SLAB  Staging Kainatty side 6 4 2 2 0 0 2 0    
13 BEAM/SLAB  Bar bending and Fixing Kainatty side 6 4 2 2 0 0 2 0    
14 BEAM/SLAB  Shuttering  and Concreting  Kainatty side 6 4 2 2 0 0 2 0    
15 BEAM/SLAB  Staging Nadapuram side 9 7 2 1 0 0 1 0    
16 BEAM/SLAB  Bar bending and Fixing Nadapuram side 9 7 2 2 1 0* 1 1   P7-P8 girder concrete completed.
17 BEAM/SLAB  Shuttering  and Concreting  Nadapuram side 9 7 2 2 1 0* 1 2   P8-P9 girder concrete complete
18 BEAM/SLAB KAINATTY  SIDE 6 4 2 2 1 0 2 0    
19 BEAM/SLAB NADAPURAM SIDE 9 7 2 2 0* 0* 2 1   steel work of P7-P8 and P8-P9 slab in progress.
20 HR/FP/KERB KAINATTY  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
21 HR/FP/KERB NADAPURAM SIDE 100% 40% 60% 0 0.00% 0.00% 0.00% 0.00%    
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
Availbility of Men               
Date 26-11-11 27-11-11 28-11-11 29-11-11 30-11-11 12-01-2011 12-02-2011
Nof labours 30 30 30 30 30 30 30

 

Description

 

Completed/Progress

 

Remarks

Pile Concreting (Total no of piles - 45) completed  
Pile cap ( Total no. of pile cap 15) In progress Done 14 nos.
Pile cap at P4 location completed  
Pier concreting ( Total no. of pier  15) In progress Done14nos.
Pier cap( Total no. of pier cap 15) In progress Done 14 nos.
Slab concreting In progress Done 10 no.
Road work( diversion road) completed Nadapuram side.
 RE wall panel casting (total 440) In progress Done 200 Nadapuram side, Done 200 Kainatty side
Hand rail casting horizontals In progress Done 900 nos.
P8-P9 girder  completed done concrete.
P7-P8 girder reinforcement completed  
P7-P8 girder shuttering In progress done concrete.
Excavation for pile cap at P6 location  completed Pier completed. 
RE wall excavation Nadapuram side In progress Pcc and RCC works in progress.
Repair work of diversion road In progress  
 