Prevoius Weekly Reports

   Weekly progress report as on 25.11.11
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PILE  CALICUT  SIDE

48

48

0

0

4

4

1

4

 

 

2

PILE THIRUR SIDE

24

8

16

0

4

4

0

4

 

 

3

PILE CAP CALICUT  SIDE

12

10

2

0

1

0

1

1

 

 

4

PILE CAP  THIRURSIDE

6

0

6

0

0

0

0

0

 

 

5

PIER CALICUT SIDE

12

9

3

0

2

2

0

1

 

 

6

PIER THIRUR SIDE

6

0

6

0

0

0

0

0

 

 

7

PIER CAPCALICUT   SIDE

12

2

10

0

1

1

0

1

 

staging @ p8 completed

8

PIER CAP THIRUR SIDE

6

0

6

0

0

0

0

0

 

 

9

RE/R WALL CALICUT   SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

10

RE/R WALLTHIRUR SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

11

BEAM/SLAB CALICUT   SIDE

12

0

12

0

0

0

0

0

 

 

12

BEAM/SLAB THIRUR SIDE

6

0

6

0

0

0

0

0

 

 

13

HR/FP/KERB CALICUT   SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

14

HR/FP/KERBTHIRUR SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

15

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

  

 

 