   Weekly progress report as on 25.11.2011
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PILE CHERUVATHOOR  SIDE

27

21

6

2

0

0

0

0

 

 

2

PILE PADANNA SIDE

24

13

11

2

3

0

5

3

 

winch breakdown

3

PILE CAP CHERUVATHOOR SIDE

9

4

5

1

2

0

3

1

 

 

4

PILE CAP  PADANNA SIDE

8

1

7

0

0

0

1

2

 

 

5

PIER CHERUVATHOOR SIDE

9

2

7

0

1

1

0

1

 

P13 pier completed

6

PIER PADANNA SIDE

8

0

8

0

0

0

0

0

 

 

7

PIER CAP CHERUVATHOOR SIDE

9

1

8

0

2

1

1

0

 

P15 pier cap complete

8

PIER CAP PADANNA SIDE

8

0

8

0

0

0

0

0

 

 

9

RE/R WALL CHERUVATHOOR  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

10

RE/R WALL PADANNA SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

11

BEAM/SLAB CHERUVATHOOR  SIDE

9

0

9

0

0

0

0

0

 

 

12

BEAM/SLAB PADANNA SIDE

8

0

8

0

0

0

0

0

 

 

13

HR/FP/KERB CHERUVATHOOR  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

14

HR/FP/KERB PADANNA SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

15

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

  

 

Availbility of Men               
Date 19-11-2011 20-11-2011 21-11-2011 22-11-2011 23-11-2011 24-11-2011 25-11-2011
Nof labours 20 20 20 20 27 27 27
               
Material Stocking Status Required Available Remarks        
Coarse Aggreagate (m3) available            
Fine Aggreagate(m3) available            
Cement(bag) 450 136          
Steel(MT) 10 20          
               
               
Utility shifting              
Utilities to be shifted Status Remarks          
BSNL AP1,P9,P10 to be shifted            
KSEB in progress utility shifting near AP2 complete,
estimation yet to be received,P4 location shifted.
     
KWA currently can be managed at site             
Others              

 

 
Back
 
    
WATER LOGGED AREA P11 LOCATION

    
    
STAGING WORK IP AT AP2-P15

    
    
PILE CHIPPING IP AT P3 LOCATION

    
    
P15 PIER BEAM COMPLETE

    
 
    
P13 PIER BEAM IP

    
    
P2 EXCAVATED FOR PILE CAP

      
 

 

 

 

 

 

 

 