   24.02.2010
    

ROB at Koratty

PROGRESS AS ON 20.02.2010

 

Work Planned upto 20/02/2010 Completed / Progress Remarks
P4-P5 Span Staging work Completed  
Concreting girders - 3 nos. Completed  
Stressing girders Completed  
Shuttering work for cross beam & slab Completed  
Reinforcement work for slab In Progress  
Approval of GAD by railways- follow up to be done by contractor   Delay in GAD approval
Box culvert works (under pass) Not started Contractor agreed to start under pass, water line and telephone line to be shifted for excavation
 