Prevoius Weekly Reports

   Weekly progress report as on 25.11.2011
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PILE SHORNUR  SIDE

9

9

 

 

 

Completed

 

 

 

2

PILE M.C SIDE

36

36

 

 

 

Completed

 

 

 

 

3

PILE CAP SHORNUR SIDE

3

3

 

 

 

Completed

 

 

 

 

4

PILE CAP  M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

5

PIER SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

 

6

PIER M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

7

PIER CAP SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

 

8

PIER CAP M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

9

RE/R WALL SHORNUR SIDE

100%

39

61%

0

10.00%

0.00%

63.00%

15.00%

0

Concreting could not be done even though the shuttering is complete for 12 metres in the RCC retaining wall due to SHORTAGE OF CEMENT.

10

RE/R WALL M.C SIDE

100%

9

91%

0

5.00%

0.00%

13.00%

10.00%

0

Excavation for RE wall completed at M.C side.Balance works could not be done in the approach portion because of CEMENT SHORTAGE

11

BEAM/SLAB SHORNUR  SIDE

3

2

1

0

0

0

0

0

0

 

12

BEAM/SLAB M.C SIDE

12

11

1

0

1

1

0

0

0

deshuttering of the span P5-P4  completed and P3-P4 almost completed.

13

HR/FP/KERB SHORNUR  SIDE

100%

50

50%

0

0.00%

0.00%

0.00%

0.00%

0 days

Inner kerb shuttering and reinforcement works in progress at AP1-P1.Concreting could not be done due to SHORTAGE OF CEMENT

14

HR/FP/KERB M.C SIDE

100%

53

47%

0

8.00%

1.00%

6.00%

8.00%

 

Expansion joint works   at locations P7 and P8 completed.

15

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

  

 

Availbility of Men               
Date 19-11-2011 20-11-2011 21-11-2011 22-11-2011 23-11-2011 24-11-2011 25-11-2011
Nof labours 19 18 18 19 20 19 20
               
Material Stocking Status              
  Required Available Remarks        
Fine aggregate {cft} 300 350          
Cement(bag) 650 420 stock replendished only today        
Steel inT 11 12          
Coarse Aggreagate (cft) 300 400          

 

Utility shifting  
Utilities to be shifted  
BSNL COMPLETED
KSEB COMPLETED
KWA COMPLETED
Others COMPLETED 

 

 

 