ROB at Ponnurunni |
|
|
Pile Concreting |
in progress |
Done 28 nos |
Pile cap |
In progress |
Done 7 nos |
Pier concreting |
In progress |
Done 7 nos |
Pier cap |
In progress |
Done 7 nos, |
P15,AP2 pedestal concrete |
completed |
|
staging for P15-AP2 girder |
Completed |
|
AP2-P15 girder reinforcement |
Completed |
|
AP2-P15 girder concreting |
Completed |
02.11.11 |
AP2-P15I st stage stressing |
Completed |
17.11.11 |
AP2-P15 II nd stage stressing |
Completed |
19.11.11 |
P15-P14 girder staging |
Completed |
|
P15-P14 girder reinforcement |
completed |
|
P15-P14 girder concreting |
completed |
on 11.11.11 |
P15-P14 girder stressing |
|
planned on 25.11.11 |
P14-P13 girder shuttering |
In progress |
|
P14-P13 reinforcement |
completed |
|
P14-P13 side shuttering |
In progress |
|
Electricity line shifting for P9 location |
completed |
|
Electricity line shifting for RE wall at Palarivattom side |
not done |
Sub Engineer inspected site on 03.11.11. Workers came to site on 05.11.11 and it was observed that there are KWA pipe lines running parallel to road and shifting posts to new location cannot be done in the usual procedure. They have instructed the RBDCK to submit a letter agreeing to remit the additional expenses incurred for this as per the actuals.They have assured to commence the works immediately on receipt of the letter. RBDCK agreed.Letter sent. Mr. Viju AE KSEB informed that the line stringing at Vytila side will be taken up on 17.11.11 and completed this week itself. He has agreed to take up palarivattom side post shifting immediately after that. Will be done on 25.11.11. |
Railway trees cut near P11, RP1 |
completed |
Location cleared for piling |
KWA lines shifting towards Vyttila side |
In progress |
Fabricated flanges will reach site on 07.11.11. AE KWA was requested to commence works on palarivattom side.EE, KWA informed that the works of linking the new line to the existing one will be completed by 14.11.11.Linking works resumed on 17.11.11 and expects to be complete by 20.11.11. On 21.11.11 some mismstch was found in the fabricated items and work is suspended for the correction of the same. Expected to resume on 28.11.11. One more week required for the completion. |
KSEB 2 overhead line shifting |
completed |
|
KSEB utility shifting |
|
KSEB post shifting in progress |
Pile P9 KWA line shifting |
pending |
water supply line to railway broke at 07-05-2011 |
Pile load test P14, P4 |
completed |
|
RE Wall panel casting (355nos) |
completed |
done 355nos |
Shifting of railway signal cable at RP1 |
completed |
completed on 01.11.11.Rail tel cable shifting will be complete by 12.11.11.completed on 12.11.11.Piling expected to resume on 21.11.11. |
Working over KRL pipe lines for RP1 |
|
KRL objected the placing of the piling RIgs on their Corridor over lapping with vytila thammanam PWD road. Joint site inspection was held on 23.11.11 with KRL, RLY, RBDCK, KITCO & CVCC . Decision from KRL regarding precautions to be done at site awaited. |
Pedestal P11 |
completed |
|