Prevoius Weekly Reports

   Weekly progress report as on 25.11.2011
    

 

Si No

Activity Description

Total Quantity

Cumulative progress upto 24.11.11

Balance  work up to 24.11.11

Cumulative delay in Qty up to 24.11.11

Work  planned  during the week

Actual work done during the week

delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

1

PILE  Palarivattom side(Approach portion)

31

28

3

0

0

0

0

0

kwa line to be shifted

2

PILE Palarivattom side(railway portion)

6

0

6

0

0

0

0

0

"      "

3

PILE vytilla side(Approach portion)

42

0

42

0

0

0

0

0

"      "

4

PILE vytilla side(railway portion)

6

0

6

0

0

0

0

0

"      "

5

PILE CAP Palarivattom side(Approach portion)

8

7

1

1

1

1

0

0

"      "

6

PILE CAP Palarivattomside(railway portion)

1

0

1

0

0

0

0

0

"      "

7

PILE CAP vytilla side(Approach portion)

9

0

9

0

0

0

0

0

"      "

8

PILE CAP vytilla side(railway portion)

1

0

1

0

0

0

0

0

"      "

9

PIER Palarivattom side(Approach portion)

8

7

1

0

3

1

0

0

 

10

PIER Palarivattomside(railway portion)

1

0

1

0

0

0

0

0

 

11

PIER Vytilla side(Approach portion)

9

0

9

0

0

0

0

0

"      "

12

PIER vytilla side(railway portion)

1

0

1

0

0

0

0

0

"      "

13

PIER  CAP Palarivattom side(Approach portion)

8

7

1

0

0

0

2

2

 

14

GIRDER Palarivattom side(Approach portion)

7

2

5

0

1

0

1

0

 

15

PIER CAP Palarivattomside(railway portion)

1

0

1

0

0

0

0

0

 

16

PIER CAP  Vytilla side(Approach portion)

9

0

9

0

0

0

0

0

"      "

17

PIER CAP vytilla side(railway portion)

1

0

1

0

0

0

0

0

"      "

18

RE WALL PANEL

355

355

0

0

0

1

0

0

 

Labour Report              
               
Date 18.11.11 19.11.11 20.11.11 21.11.11 22.11.11 23.11.11 24.11.11
Day Fri Sat Sun Mon Tue Wed Thurs
Climate sunny  sunny  sunny  sunny  sunny  sunny  sunny 
No.of labours 26 25 20 27 24 22 26 

 

Availability of Material     
     
Materials Required for week ending on 01.12.11 Available as on 24.11.11
Fine aggregate(M3) Ready Mix Concrete
Coarse aggregate(M3)
Cement(BAG)
Steel(TONN) 2.5 40 

 

Description Completed/ Progress Remarks
ROB at Ponnurunni    
Pile Concreting  in progress Done 28 nos
Pile cap In progress Done 7 nos
Pier concreting In progress Done 7 nos 
Pier cap  In progress Done 7 nos, 
P15,AP2 pedestal concrete  completed  
staging for P15-AP2 girder Completed  
AP2-P15 girder reinforcement Completed  
AP2-P15 girder concreting Completed 02.11.11
AP2-P15I st stage stressing Completed 17.11.11
AP2-P15 II nd stage stressing Completed 19.11.11
P15-P14 girder staging Completed  
P15-P14 girder reinforcement completed  
P15-P14 girder concreting completed on 11.11.11
P15-P14 girder stressing   planned on 25.11.11
P14-P13 girder shuttering In progress  
P14-P13 reinforcement  completed  
P14-P13 side shuttering  In progress  
Electricity line shifting for P9 location completed  
Electricity line shifting for RE wall at Palarivattom side not done Sub Engineer inspected site on 03.11.11. Workers came to site on 05.11.11 and it was observed that there are KWA pipe lines running parallel to road and shifting posts to new location cannot be done in the usual procedure. They have instructed the RBDCK to submit a letter agreeing to remit the additional expenses incurred for this as per the actuals.They have assured to commence the works immediately on receipt of the letter. RBDCK agreed.Letter sent. Mr. Viju AE KSEB informed that the line stringing at Vytila side will be taken up on 17.11.11 and completed this week itself. He has agreed to take up palarivattom side post shifting  immediately after that. Will  be done on 25.11.11.
Railway trees cut near P11, RP1 completed Location cleared for piling
KWA lines shifting towards Vyttila side In progress Fabricated flanges will reach site on 07.11.11. AE KWA was requested to commence works on palarivattom side.EE, KWA informed that the works of linking the new line to the existing one will be completed by 14.11.11.Linking works resumed on 17.11.11 and expects to be complete by 20.11.11.  On 21.11.11  some mismstch was found in the fabricated items and work is suspended for the correction of the same. Expected to resume on 28.11.11. One more week required for the completion.
KSEB 2 overhead line shifting completed  
KSEB utility shifting    KSEB post shifting in progress
Pile P9 KWA line shifting pending water supply line to railway broke    at 07-05-2011 
Pile load test P14, P4 completed  
RE Wall panel casting (355nos) completed done 355nos
Shifting of railway signal cable at RP1 completed completed on 01.11.11.Rail tel cable shifting will be complete by 12.11.11.completed on 12.11.11.Piling expected to resume on 21.11.11. 
Working over KRL pipe lines for RP1   KRL objected the placing of the piling RIgs on their Corridor over lapping with vytila thammanam PWD road. Joint site inspection was held on 23.11.11 with KRL, RLY, RBDCK, KITCO & CVCC . Decision from KRL regarding precautions to be done at site awaited.
Pedestal P11 completed   
 
Back
 
    
STRAND INSERTION P15 P14

    
    
KSEB LINE SHIFTING AT VYTILA SIDE

    
    
II ND STAGE STRESSING A2 P15

    
    
DESHUTTERING P15 P14

    
 
    
BENTONITE TANK FOR RP1 AT KRL LAND

      
 

 

 

 

 

 

 

 