|
Prevoius Weekly Reports
|
19-07.2010 |
|
ROB at Bakel
PROGRESS OF ROB WORK AS ON 10-07.2010 |
Work Planned upto 10-07-2010 |
Completad / Progress |
Remarks |
Span of Kasargod side |
|
|
Concreating Beam and Slab |
Completed |
|
Hand Rail & Foot Path Casting |
In progress |
|
Outer Kerb Casting |
Completed |
|
|
|
Back |
|
No images are uploaded for this Weekly Reports
|
|
|