   weekly progress 25.11.2011
    

 

SlNo

Activity –which can be completed without caution

Description

Total Quantity

Cumulative progress up to this week

(1)

Balance  work

(2)

Cumulative delay in weeks after

Spplagmnt

(3)

Work  planned  during the week

(4)

Actual work done during the last week

(5)

Short fall in the last week 

(6)

Work 

Planned for next week

(7)

No of days remaining for completion as per the weekly plan

Remarks

1

Re wall towards NH side

100%

34

66

32

 

 

0

0

 0

.

3

Approach

 Span

 

5

 

5

0

37

-

-

-

-

 

 

4

Pier cap

2

2

0

46

 0

 0

 0

 0

 0

 

 

 

5

Pile (Rly)pulikakadavuside

4

 

4

0

60

 0

 0

0

 

6

Pile (Rly)Nhside

4

4

0

60

0

0

0

0

0

 

6

Piers (Rly)

 

2

2

0

51

 0

 0

 0

 0

 

Work of the trestle column in progress very slowly due to ”shortage of labour”

9

R0AD WORK

{WBM} towards pulikkakadavuside

100%

90

 

0

 

 

 

 

 

 

 

1O

Kerb/handrail  (approach portion)N.H side

200m

Inner kerbconcreting complete for a distance of  25 metres.Handrailposts  concreted for a. distance of 50 metres.Nowork in the last week.

 

Nil

 

 

 

 

 

 

12

Friction slab  approach portion(N.H side

200m

 

No work in the last week

 

 

 

 

     

 

 

 

 

 
Back
 
    
SHUTTERING WORK FOR TRESTLE COLUMN AT P8

    
    
SHUTTERING WORK AT TRESTLE COLUMN IN PROGRESS

    
    
SHUTTERING WORK AND REINFORCEMENT FOR TRESTLE COLUMN AT P8

    
    
RAILWAY PORTION AT P8

    
 
    
RAILWAY LOCATION.NO WORK

      
 

 

 

 

 

 

 

 