   Report as on 18.11.2011
    

 

Progress Report For Cheruvathoor  ROB for the week ending on 18-11-2011

 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PILE CHERUVATHOOR  SIDE

27

21

6

2

0

0

0

0

 

 

2

PILE PADANNA SIDE

24

12

12

0

3

1

2

3

 

P5 a complete

3

PILE CAP CHERUVATHOOR SIDE

9

3

6

0

2

1

1

2

 

P8 pile cap complete

4

PILE CAP  PADANNA SIDE

8

1

7

0

0

0

1

0

 

P6  pile cap complete

5

PIER CHERUVATHOOR SIDE

9

1

8

0

1

1

0

1

 

P15 completed

6

PIER PADANNA SIDE

8

0

8

0

0

0

0

0

 

 

7

PIER CAP CHERUVATHOOR SIDE

9

0

9

0

2

1

1

2

 

AP2 pier cap complete

8

PIER CAP PADANNA SIDE

8

0

8

0

0

0

0

0

 

 

9

RE/R WALL CHERUVATHOOR  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

10

RE/R WALL PADANNA SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

11

BEAM/SLAB CHERUVATHOOR  SIDE

9

0

9

0

0

0

0

0

 

 

12

BEAM/SLAB PADANNA SIDE

8

0

8

0

0

0

0

0

 

 

13

HR/FP/KERB CHERUVATHOOR  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

14

HR/FP/KERB PADANNA SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

15

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

16

Deck Slab

 

 

 

 

 

 

 

 

 

 

17

Utility shifting

 

 

 

 

 

 

 

 

 

 

 

 

Availbility of Men

 

 

 

 

 

 

 

 

Date

05-12-2011

13/6/2011

14/7/2011

15/8/2011

16/9/2011

17/10/2011

18/11/2011

 

Nof labours

27

0

27

33

15

15

20

 

 

 

 

 

 

 

 

 

 

Material Stocking Status

Required

Available

Remarks

 

 

 

 

 

Coarse Aggreagate (m3)

available

 

 

 

 

 

 

 

Fine Aggreagate(m3)

available

 

 

 

 

 

 

 

Cement(bag)

450

40

 

 

 

 

 

 

Steel(MT)

10

25

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Utility shifting

 

 

 

 

 

 

 

 

Utilities to be shifted

Status

Remarks

 

 

 

 

 

 

BSNL

AP1,P9,P10 to be shifted

 

 

 

 

 

 

 

KSEB

in progress

utility shifting near AP2 complete,
estimation yet to be received,P4 location shifted.

 

 

 

 

KWA

currently can be managed at site

 

 

 

 

 

 

 

Others

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

AREAS OF  CONCERN AND CORRECTIVE ACTION:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Water logging at P11,P12,P14 . Bunds in progress ,pumping out water in progress.

Earth filling in progress for service road

 

 

 

 

 

 

 

Land acquisition at AP1(BSNL) and P9 not yet done.

 

 

 

 

 

 

 
Back
 
    
PADANNA AREA SITE CLEARING IP

    
    
P13 PIER READY FOR CONCRETE

    
    
P13 PIER BEAM SHUTTERING & REINF IN PROGRESS

    
    
P11 LOCATION

    
 
    
P8 PILE CAP SHUTTERING & REINF COMPLETE

    
    
P5 B BORING

      
 

 

 

 

 

 

 

 