Progress Report For Payyannur ROB for the week ending on18-11-2011 |
Si No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
Remarks |
1 |
PILE THRIKKARIPUR SIDE |
33 |
33 |
0 |
0 |
0 |
0 |
0 |
0 |
|
2 |
PILE EZHIMALA SIDE |
27 |
27 |
0 |
0 |
0 |
0 |
0 |
0 |
|
3 |
PILE PAYYANNUR SIDE |
27 |
27 |
0 |
0 |
0 |
0 |
0 |
0 |
|
4 |
PILE CAP THRIKKARIPUR SIDE |
11 |
11 |
0 |
0 |
0 |
0 |
0 |
0 |
|
5 |
PILE CAP EZHIMALA SIDE |
9 |
9 |
0 |
0 |
0 |
0 |
0 |
0 |
|
6 |
PILE CAP PAYYANNUR SIDE |
9 |
9 |
0 |
0 |
0 |
0 |
0 |
0 |
|
9 |
PIER THRIKKARIPUR SIDE |
11 |
11 |
0 |
0 |
0 |
0 |
0 |
0 |
|
8 |
PIER EZHIMALA SIDE |
9 |
9 |
0 |
0 |
0 |
0 |
0 |
0 |
|
9 |
PIER PAYYANNUR SIDE |
9 |
9 |
0 |
0 |
0 |
0 |
0 |
0 |
|
10 |
PIER CAP THRIKKARIPUR SIDE |
11 |
11 |
0 |
0 |
0 |
0 |
0 |
0 |
|
11 |
PIER CAP EZHIMALA SIDE |
9 |
9 |
0 |
0 |
0 |
0 |
0 |
0 |
|
12 |
PIER CAP PAYYANNUR SIDE |
9 |
9 |
0 |
0 |
0 |
0 |
0 |
0 |
|
16 |
RE/R WALL THRIKKARIPUR SIDE |
100% |
65% |
35% |
0 |
10.00% |
10.00% |
5.00% |
10.00% |
|
17 |
RE/R WALL EZHIMALA SIDE |
100% |
55% |
45% |
0 |
5.00% |
5.00% |
0.00% |
5.00% |
|
18 |
RE/R WALL PAYYANNUR SIDE |
100% |
10 |
90% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
19 |
BEAM/SLAB Staging Thrikkaripur side |
10 |
10 |
0 |
0 |
0 |
0 |
0 |
0 |
|
20 |
BEAM/SLAB Bar bending and Fixing Thrikkaripur side |
10 |
10 |
0 |
0 |
0 |
0 |
0 |
0 |
|
21 |
BEAM/SLAB Shuttering and Concreting Thrikkaripur side |
10 |
10 |
0 |
0 |
0 |
0 |
0 |
0 |
|
22 |
BEAM/SLAB Staging Ezhimala side |
7 |
7 |
0 |
0 |
0 |
0 |
0 |
0 |
|
23 |
BEAM/SLAB Bar bending and Fixing Ezhimala side |
7 |
7 |
0 |
0 |
0 |
0 |
0 |
0 |
|
24 |
BEAM/SLAB Shuttering and Concreting Ezhimala side |
7 |
7 |
0 |
0 |
0 |
0 |
0 |
0 |
|
25 |
BEAM/SLAB Staging Payyanur side |
10 |
8 |
2 |
2 |
0 |
0 |
2 |
0 |
|
26 |
BEAM/SLAB Bar bending and Fixing Payyanur side |
10 |
8 |
2 |
2 |
0 |
0 |
2 |
0 |
|
27 |
BEAM/SLAB Shuttering and Concreting Payyanur side |
10 |
8 |
2 |
2 |
0 |
0 |
2 |
0 |
|
28 |
BEAM/SLAB THRIKKARIPUR SIDE |
10 |
10 |
0 |
0 |
0 |
0 |
0 |
0 |
|
29 |
BEAM/SLAB EZHIMALA SIDE |
7 |
7 |
0 |
0 |
0 |
0 |
0 |
0 |
|
30 |
BEAM/SLAB PAYYANNUR SIDE |
10 |
8 |
2 |
2 |
0 |
0 |
2 |
0 |
|
31 |
HR/FP/KERB THRIKKARIPUR SIDE |
100% |
30% |
70% |
30% |
0.00% |
0.00% |
0.00% |
30.00% |
|
32 |
HR/FP/KERB EZHIMALA SIDE |
100% |
30% |
70% |
30% |
10.00% |
0.00% |
0.00% |
0.00% |
|
33 |
HR/FP/KERB PAYYANNUR SIDE |
100% |
100% |
0% |
0 |
40.00% |
40.00% |
0.00% |
0.00% |
|
34 |
BC/PAINTING |
100% |
0 |
100% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
|
|
|
|
|
|
|
|
|
|
|
|