   weekly progress 18.11.2011
    

 

Progress Report For Pulianam  ROB for the week ending on 18.11.2011                     
Sl No   Activity Description   Total Quantity  Cumulative progress upto last week   Balance  work up to last week  Cumulative delay in Qty up to last week  Work  planned  during the week   Actual work done during the week   Cumulative delay in Qty up to this week  Work  Planned for next week   Remarks 
1 Pile towards NH side 26 26 0 0 0 0 0 0 TARGET ACHIEVED
2 Pile towards Puliyanam side 18 18 0 0 1 1 0 0 TARGET ACHIEVED
3 Pile cap at NH  Side 6 6 0 0 0 0 0 0 TARGET ACHIEVED
4 Pile Cap at Pulianam side 4 4 0 0 0 0 0 0 TARGET ACHIEVED
5 RC wall at Puliyanam side 100% 30% 70% 0 0% 5% 0% 5%  
6 RC wall at NH side 100% 10% 90% 0 0% 5% 0% 5%  
7 Pier at NH Side 6 5 1 0 0 0 0 1  
8 Pier at Puliyanam Side 4 4 0 0 0 0 0 0 TARGET ACHIEVED
9 Piercap at NH Side 6 5 1 0 0 0 0 1  
10 Piercap at Puliyanam 4 4 0 0 0 0 0 0 TARGET ACHIEVED
11 PEDESTAL 10 2 8 0 1 1 0 1  
                     
Date 12.11.11 14.11.11 15.11.11 16.11.11 17.11.11 18.11.11        
Climate pleasant pleasant pleasant pleasant pleasant pleasant        
No.of labours 50 54 53 55 54 54        
                     
availability of material                  
materials Required Available                
Fine aggregate(M3) 6 10                
Coarse aggregate(M3) 12 20                
Cement(BAG) 100 550                
Steel(TONN) 5 66                
                     
 
Back
 
    
STAGING (P8-P9)COMPLETED 17.11.11

    
    
RC WALL PULIYANAM SIDE CONCRETING 12.11.11

    
    
RC WALL NH SIDE CONCRETED 15.11.11

    
    
PIER CAP P1 CONCRETE 14.11.11

    
 
    
P8-P9 STAGING FOR SLAB 15.11.11

    
    
P6 BOTTOM HAUNCH 16.11.11

      
 

 

 

 

 

 

 

 