PROGRESS OF ROB and ROAD WORK AS ON 18-11-2011 |
|
Description |
Completed/ Progress |
Remarks |
IV |
ROB at Parappanangady |
|
|
|
Pier cap (Total no of pier Cap- 21) |
Completed |
19 NOS COMPLETED |
|
RE Wall panel casting ( total 550 nos) |
Completed |
|
|
Slab calicut side (total 10 nos ) |
In progress |
9nos done |
|
slab NH side ( 11 nos) |
In progress |
10 nos done |
|
Retaining wall NH side |
In progress |
Done LHS -90%, RHS- 90% |
|
Dirt wall AP1 concreting |
In progress |
Done 90% |
|
Handrail casting |
In progress |
1000 nos completed. |
|
Handrail fixing |
In progress |
NH side 3 slab completed. |
|
Boring at RP1,RP4 |
In progress |
RP-4 first pile concreted. |
|
NH side RE panel erection |
In progress |
0.4% completed. |
|
RE wall excavation Calicut side |
Completed |
Foundation design should summit by contractor. |
|
expansion joint NH side completed |
In progress |
9 nos completed. |