   weekly progress 18.11.2011
    

 

PROGRESS OF ROB and ROAD  WORK AS ON 18-11-2011
  Description Completed/ Progress Remarks
IV ROB at Parappanangady    
  Pier cap (Total no of pier Cap- 21) Completed 19 NOS COMPLETED
  RE Wall panel casting ( total 550 nos) Completed  
  Slab calicut side  (total 10 nos ) In progress 9nos done
  slab NH side ( 11 nos) In progress 10 nos done
  Retaining wall NH side In progress Done LHS -90%, RHS- 90%
  Dirt wall AP1 concreting  In progress Done 90%
  Handrail casting In progress 1000 nos completed.
  Handrail fixing In progress NH side 3 slab completed.
  Boring at RP1,RP4 In progress RP-4 first pile concreted.
  NH side RE panel erection In progress 0.4% completed.
  RE wall excavation Calicut side Completed Foundation design should summit by contractor.
  expansion joint NH side completed In progress 9 nos completed. 
 
Back
 
    
WORK OF SERVICE ROAD STARTED

    
    
RP4-3,PILE CONCRETING 2. (2

    
    
RE WALL WORKS

    
    
LINER REMOVING IN RP1.

    
 
    
HANDRAIL FIXING AP2 SIDE..

    
    
BORING IN RP4

      
 

 

 

 

 

 

 

 