   Report as on 11-11-11
    

 

Progress Report For Koilandy ROB for the week ending on 11-11-2011  
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE Muthambi side 27 18 9 0 0 0 0      
2 PILE Thamarassery side 33 8 25 0 6 2 0 5    
3 PILE NH SIDE 30 5 30 0 4 2 0 5    
4 PILE CAP Muthambi SIDE 9 0 9 0 2 0 0 2   P15,P14,P13 pile cap excavation, chipping and PCC Complete
4 PILE CAP Thamarassery SIDE 11 0 11 0 0 0 0 0    
5 PILE CAP NH SIDE 10 0 10 0 0 0 0 0    
6 PIER Muthambi  SIDE 9 0 9 0 0 0 0 0    
7 PIER Thamarassery SIDE 11 0 11 0 0 0 0 0    
8 PIER NH SIDE 10 0 10 0 0 0 0 0    
9 PIER CAP Muthambi  SIDE 9 0 9 0 0 0 0 0    
10 PIER CAP Thamarassery SIDE 11 0 11 0 0 0 0 0    
11 PIER CAP NH SIDE 10 0 10 0 0 0 0 0    
12 RE/R WALL Muthambi side 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
13 RE/R WALL Thamarassery side SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
14 RE/R WALL NH SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
15 BEAM/SLAB Muthambi SIDE 8 0 8 0 0 0 0 0    
16 BEAM/SLAB Thamarassery SIDE 10 0 10 0 0 0 0 0    
17 BEAM/SLABNH SIDE 10 0 10 0 0 0 0 0    
18 HR/FP/KERB Muthambi SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
19 HR/FP/KERB thamarassery SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
20 HR/FP/KERB NH SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
21 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
22 Deck Slab                    
23 Utility shifting                   KSEB estimate received, RBDCK DD handed over to KSEB 

 

Availbility of Men               
Date 11-05-2011 11-06-2011 11-07-2011 11-08-2011 11-09-2011 11-10-2011 11-11-2011
Nof labours 45 45 45 45 45 45 45
               
Material Stocking Status Required Available Remarks        
Coarse Aggreagate (m3) 100 120          
Fine Aggreagate(m3) 100 120          
Cement(bag) 1000 400          
Steel(MT) 15 23          
               
               
Utility shifting              
Utilities to be shifted Status Remarks          
BSNL              
KSEB              
KWA              
Others              
 
Back
 
    
PILE P4C BORING

    
    
PILE P1B BORING

    
    
PILE AP1C BORING

    
    
PILE 26A BORING

    
 
    
PILE 25B CONCRETING

    
    
PILE 25 C CONCRETING

    
    
PILE 23B BORING

    
 
 
 

 

 

 

 

 

 

 